3824 N MOUND VIEW AVE 91604
Certificate Information: 3824 N MOUND VIEW AVE 91604
- Application / Permit
- 23016-20000-31320
- Plan Check / Job No.
- B23VN12443
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 17' X 19' DET GARAGE INTO A (N) 323 SF ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). "COMPLY WITH DEPARTMENT ORDER effective date 07/17/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 10/11/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2023 | JESSE ARELLANO |
| Corrections Issued | 9/19/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 9/20/2023 | APPLICANT |
| Issued | 10/11/2023 | APPLICANT |
| CofO in Progress | 4/2/2024 | ARAM AVAKIAN |
| CofO Issued | 1/27/2025 | DANIEL SANCHEZ |
| Permit Finaled | 1/27/2025 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 9/22/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 9/22/2023 | TAL SHEMEN |
| Grading Pre-Inspection | Cleared | 10/5/2023 | MANUEL TEJADA |
Contact Information
| Contractor | J'S Vision Construction Inc; Lic. No.: 1043336-B | 5614 FULCHER AVE NORTH HOLLYWOOD, CA 91601 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/24/2023 | Approved | PATRICK LIEBREGT |
| Deputy Drilled-In Anchors | 12/12/2023 | Conditional Approval | TIMOTHY KEY |
| Footing/Foundation/Slab | 12/15/2023 | Not Ready for Inspection | HAGOP BADOSSIAN |
| Sewer | 12/15/2023 | Approved | HAGOP BADOSSIAN |
| Underground Mechanical | 12/15/2023 | Approved | HAGOP BADOSSIAN |
| Excavation/Setback/Form/Re-Bar | 12/18/2023 | Partial Approval | ARAM AVAKIAN |
| Footing/Foundation/Slab | 12/21/2023 | Approved | ARAM AVAKIAN |
| BUILDING-Rough-Frame | 1/8/2024 | Approved | ARAM AVAKIAN |
| ELECTRICAL-Rough | 1/8/2024 | Approved | ARAM AVAKIAN |
| HVAC-Rough | 1/8/2024 | Not Ready for Inspection | ARAM AVAKIAN |
| PLUMBING-Rough | 1/8/2024 | Not Ready for Inspection | ARAM AVAKIAN |
| Insulation | 1/19/2024 | Approved | ARAM AVAKIAN |
| Interior/Exterior Lathing | 1/19/2024 | Approved | ARAM AVAKIAN |
| Drywall Nailing | 1/26/2024 | Approved | JOEL ORDAZ |
| Interior/Exterior Lathing | 1/31/2024 | Approved | ARAM AVAKIAN |
| Shower Pan | 1/31/2024 | Approved | ARAM AVAKIAN |
| HVAC-Rough | 2/14/2024 | Approved | ARAM AVAKIAN |
| Final | 4/1/2024 | OK to Issue CofO | ARAM AVAKIAN |
| Green Building Final | 4/1/2024 | Approved | ARAM AVAKIAN |
| SGSOV-Seismic Gas S/O Valve | 4/1/2024 | SGSOV Approved | ARAM AVAKIAN |
| Smoke Detectors | 4/1/2024 | Approved | ARAM AVAKIAN |