8438 N OAKDALE AVE 91306
Certificate Information: 8438 N OAKDALE AVE 91306
- Application / Permit
- 23016-20000-31291
- Plan Check / Job No.
- B23VN12437
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Convert existing 22' 3" x 20' 3" detached garage in the rear yard to new single family per SB 9. All work done per engineer.
- Permit Issued
- Issued on 1/12/2024
- Issuing Office
- Current Status
- CofO Issued on 10/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2023 | NAREG ATARIAN |
| Corrections Issued | 9/22/2023 | NAREG ATARIAN |
| Quality Review Completed | 9/28/2023 | OMID HEDAYAT |
| No Progress | 1/11/2024 | NAREG ATARIAN |
| Plan Check Approved | 1/11/2024 | NAREG ATARIAN |
| No Progress | 1/12/2024 | INTERNET PERMIT |
| Plan Check Approved | 1/12/2024 | NAREG ATARIAN |
| Issued | 1/12/2024 | APPLICANT |
| CofO in Progress | 10/16/2024 | CHRIS CHRISTENSEN |
| Permit Finaled | 10/23/2024 | JOHN JANSON |
| CofO Issued | 10/23/2024 | JOHN JANSON |
| Permit Finaled | 10/23/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/7/2023 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 10/7/2023 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 10/9/2023 | LAVEON RIDER |
| Eng Process Fee Ord 176,300 | Cleared | 10/11/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 10/11/2023 | COLIN LOREDO |
| Senate Bill 9 | Cleared | 10/18/2023 | NELSON RODRIGUEZ |
| Miscellaneous | Cleared | 10/26/2023 | RONY GIRON |
| Construction near power lines | Cleared | 12/26/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/26/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/29/2024 | Corrections Issued | JEFFREY HARTLINE |
| Excavation/Setback/Form/Re-Bar | 4/26/2024 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 4/26/2024 | Approved | JEFFREY HARTLINE |
| Sewer | 4/26/2024 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2024 | Partial Approval | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 7/1/2024 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 7/1/2024 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2024 | Partial Approval | JEFFREY HARTLINE |
| Green Building Rough | 7/1/2024 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 7/1/2024 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 7/1/2024 | Partial Approval | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 7/1/2024 | Approved | JEFFREY HARTLINE |
| Insulation | 7/5/2024 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 7/11/2024 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 7/11/2024 | Partial Approval | JEFFREY HARTLINE |
| ELECTRICAL-Final | 9/6/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| PLUMBING-Final | 9/6/2024 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 9/6/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 9/27/2024 | Approved | CHRIS CHRISTENSEN |
| Grounding or Bonding | 9/27/2024 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 9/27/2024 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 9/27/2024 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 9/27/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 9/27/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 10/2/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Service/Power Release | 10/2/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 10/4/2024 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 10/4/2024 | SGSOV Not Required | CHRIS CHRISTENSEN |
| Final | 10/15/2024 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Service/Power Release | 10/15/2024 | Approved | CHRIS CHRISTENSEN |