16614-16616 W BARNESTON ST 91344

Certificate Information: 16614-16616 W BARNESTON ST 91344

Application / Permit
23016-20000-30729
Plan Check / Job No.
B23VN12220
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: CONVERT EXISTING GARAGE TO ADU PER CA Govt. Code65852.2(e)(1)(A) WORK DONE PER WFPP
Permit Issued
Issued on 1/29/2024
Issuing Office
Current Status
CofO Issued on 12/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2023 APPLICANT
Assigned to Plan Check Engineer 9/15/2023 KHUONG TRUONG
Corrections Issued 9/18/2023 KHUONG TRUONG
Plan Check Approved 1/26/2024 KHUONG TRUONG
Issued 1/29/2024 APPLICANT
CofO in Progress 11/15/2024 JAVIER RAMOS JR
Permit Finaled 12/17/2024 RUBEN SALAS
Permit Finaled 12/17/2024 RUBEN SALAS
CofO Issued 12/17/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/25/2023 BRYAN GODINEZ
Sewer availability Cleared 10/25/2023 BRYAN GODINEZ
Construction near power lines Cleared 12/27/2023 RIDWAN HARDY
Construction within easement Cleared 12/27/2023 RIDWAN HARDY
Grading Pre-Inspection Cleared 1/23/2024 CHARLES POWELL
Eng Process Fee Ord 176,300 Cleared 1/24/2024 BRYAN GODINEZ
Miscellaneous Cleared 1/25/2024 KHUONG TRUONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/12/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 3/13/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 3/13/2024 Partial Approval JAVIER RAMOS JR
Sewer 3/13/2024 Approved JAVIER RAMOS JR
Underground Mechanical 3/13/2024 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 4/4/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 4/4/2024 Corrections Issued JAVIER RAMOS JR
Green Building Rough 4/4/2024 Approved JAVIER RAMOS JR
HVAC-Rough 4/4/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 4/4/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 4/16/2024 Approved JAVIER RAMOS JR
HVAC-Rough 4/16/2024 Approved JAVIER RAMOS JR
Insulation 4/16/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 4/16/2024 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 4/24/2024 Approved LEONARD ROSS II
Drywall Nailing 5/3/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 5/21/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 9/3/2024 Partial Inspection JAVIER RAMOS JR
Final 9/3/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 9/3/2024 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 9/3/2024 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 9/3/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 9/19/2024 Approved JAVIER RAMOS JR
Final 9/19/2024 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 9/19/2024 Approved JAVIER RAMOS JR
HVAC-Final 9/19/2024 Approved JAVIER RAMOS JR