13353-13355 W ERWIN ST 91401

Certificate Information: 13353-13355 W ERWIN ST 91401

Application / Permit
23016-20000-30715
Plan Check / Job No.
B23VN12217
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 25'-3" X 20'-8" IRREGULAR SHAPED OF (E) SFD TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK DONE PER WFPP.
Permit Issued
Issued on 10/5/2023
Issuing Office
Current Status
CofO Issued on 4/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2023 APPLICANT
Assigned to Plan Check Engineer 9/15/2023 MIROOSH KHACHATOORIAN
Corrections Issued 9/18/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 9/27/2023 ALEC MOUSAKHANIAN
Issued 10/5/2023 APPLICANT
CofO in Progress 2/26/2025 OGANES TARAKHCHYAN
Permit Finaled 4/11/2025 RUBEN SALAS
CofO Issued 4/11/2025 RUBEN SALAS
Permit Finaled 4/11/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/20/2023 TAL SHEMEN
Sewer availability Cleared 9/20/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 9/26/2023 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 6/3/2024 No Access for Inspection MICHEL ABAJAN
HVAC-Rough 6/3/2024 No Access for Inspection MICHEL ABAJAN
PLUMBING-Rough 6/3/2024 No Access for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 6/6/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 6/6/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 6/6/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 7/12/2024 Corrections Issued CHRISTOPHER ROJAS
Insulation 7/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Shower Pan 7/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Wood Frame 7/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/30/2024 Approved OGANES TARAKHCHYAN
Insulation 8/7/2024 Approved OGANES TARAKHCHYAN
Drywall Nailing 8/19/2024 Approved JACK KARGODORIAN
Interior/Exterior Lathing 9/4/2024 Approved GAREN HAYRAPETYAN
Shower Pan 9/4/2024 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 2/18/2025 Approved OGANES TARAKHCHYAN
HVAC-Final 2/18/2025 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 2/18/2025 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 2/18/2025 Approved OGANES TARAKHCHYAN
Smoke Detectors 2/18/2025 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 2/25/2025 Approved OGANES TARAKHCHYAN
Final 2/25/2025 OK to Issue CofO OGANES TARAKHCHYAN
HVAC-Final 2/25/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Final 2/25/2025 Approved OGANES TARAKHCHYAN