8754-8756 N RANCHITO AVE 91402

Certificate Information: 8754-8756 N RANCHITO AVE 91402

Application / Permit
23016-20000-30644
Plan Check / Job No.
B23VN12194
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22
Permit Issued
Issued on 10/27/2023
Issuing Office
Current Status
CofO Issued on 8/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 JESSE ARELLANO
Corrections Issued 9/15/2023 JESSE ARELLANO
Building Plans Picked Up 9/26/2023 APPLICANT
Applicant returned to address corrections 10/16/2023 JESSE ARELLANO
Issued 10/27/2023 APPLICANT
CofO in Progress 7/25/2024 GREGG CUMMINGS
CofO Issued 8/12/2024 DANIEL ORRANTE
Permit Finaled 8/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/7/2023 COLIN LOREDO
Sewer availability Cleared 10/7/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/11/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/16/2024 Partial Approval GREGG CUMMINGS
Deputy Drilled-In Anchors 2/20/2024 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 2/22/2024 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 4/19/2024 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 4/19/2024 Corrections Issued GREGG CUMMINGS
Green Building Rough 4/19/2024 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 4/19/2024 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 4/19/2024 Corrections Issued GREGG CUMMINGS
HVAC-Rough 4/23/2024 Approved GREGG CUMMINGS
PLUMBING-Rough 4/23/2024 Approved GREGG CUMMINGS
Sewer 4/23/2024 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 4/29/2024 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 4/29/2024 Approved MICHEL ABAJAN
Green Building Rough 4/29/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 4/29/2024 Approved MICHEL ABAJAN
Wood Frame 4/29/2024 Partial Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 5/2/2024 Not Ready for Inspection GREGG CUMMINGS
Wood Frame 5/2/2024 Not Ready for Inspection GREGG CUMMINGS
Insulation 5/6/2024 Partial Approval ROBERT GOLD
Shower Pan 5/6/2024 Approved ROBERT GOLD
BUILDING-Rough-Frame 5/8/2024 Approved KIRK SANDERS
Interior/Exterior Lathing 5/8/2024 Approved KIRK SANDERS
Drywall Nailing 5/15/2024 Approved VINCENT HANLEY
Final 7/19/2024 Corrections Issued MATTHEW NELSON
Green Building Final 7/19/2024 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 7/19/2024 SGSOV Approved MATTHEW NELSON
Smoke Detectors 7/19/2024 Approved MATTHEW NELSON
ELECTRICAL-Final 7/24/2024 Approved GREGG CUMMINGS
Final 7/24/2024 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 7/24/2024 Approved GREGG CUMMINGS
PLUMBING-Final 7/24/2024 Approved GREGG CUMMINGS