20165 W RINALDI ST 120 91326

Certificate Information: 20165 W RINALDI ST 120 91326

Application / Permit
23016-20000-30436
Plan Check / Job No.
B23VN12137
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Beauty Shop or Parlor
Work Description
CHANGE OF USE FROM RETAIL TO HAIR SALON
Permit Issued
Issued on 12/20/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/7/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 MARVEL DELACRUZ
Corrections Issued 9/19/2023 MARVEL DELACRUZ
Quality Review Completed 9/20/2023 OMID HEDAYAT
Building Plans Picked Up 9/22/2023 APPLICANT
Disabled Access Plans Picked Up 10/5/2023 APPLICANT
Applicant returned to address corrections 12/6/2023 MARVEL DELACRUZ
Plan Check Approved 12/20/2023 MARVEL DELACRUZ
Issued 12/20/2023 APPLICANT
CofO in Progress 3/15/2024 GREGORY POMISH
Permit Finaled 3/15/2024 JEFFREY DURAN
CofO Issued 3/15/2024 JEFFREY DURAN
Permit Finaled 3/15/2024 JEFFREY DURAN

Permit Application Clearance Information

Specific Plan Cleared 10/26/2023 SHEILA AHORAIAN
Eng Process Fee Ord 176,300 Cleared 11/1/2023 LEE GUILBEAUX
Sewer availability Cleared 11/1/2023 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 11/1/2023 LEE GUILBEAUX
"D" conditions Cleared 11/3/2023 BRENNEN OBETO
Specific Plan Cleared 11/3/2023 BRENNEN OBETO
ZA Case Cleared 11/3/2023 BRENNEN OBETO
ZI Cleared 11/3/2023 BRENNEN OBETO
DAS Clearance Cleared 11/14/2023 MARVEL DELACRUZ

Contact Information

Architect Kaltman,, I Lawrence; Lic. No.: C7405 15519 HUSTON STREET      ENCINO, CA 91436
Architect Silva,, Michael Dean; Lic. No.: C12976 P O BOX 260192      ENCINO, CA 91426
Contractor J C O R Inc; Lic. No.: 872762-B P O BOX 26864      OVERLAND PARK, KS 66225

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 1/9/2024 Partial Inspection DEANDRE HOFFMAN
Drywall Nailing 1/12/2024 Partial Approval DEANDRE HOFFMAN
Drywall Nailing 1/23/2024 Partial Approval DEANDRE HOFFMAN
Special/Order Compliance 1/24/2024 Partial Inspection DEANDRE HOFFMAN
T-Bar Ceiling 1/26/2024 Not Ready for Inspection DEANDRE HOFFMAN
Special/Order Compliance 1/30/2024 Not Ready for Inspection DANNY RODRIGUEZ
T-Bar Ceiling 1/30/2024 Partial Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 2/1/2024 Partial Inspection DEANDRE HOFFMAN
T-Bar Ceiling 2/7/2024 Conditional Approval DEANDRE HOFFMAN
Pre-Inspection 2/15/2024 Partial Inspection DEANDRE HOFFMAN
Final 2/16/2024 Corrections Issued DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 2/16/2024 SGSOV Approved DEANDRE HOFFMAN
Smoke Detectors 2/16/2024 Approved DEANDRE HOFFMAN
Wood Frame 2/16/2024 Approved DEANDRE HOFFMAN
Final 3/13/2024 OK to Issue CofO DEANDRE HOFFMAN
Special/Order Compliance 3/14/2024 Partial Inspection DEANDRE HOFFMAN