7013 N TAMPA AVE 91335

Certificate Information: 7013 N TAMPA AVE 91335

Application / Permit
23016-20000-30379
Plan Check / Job No.
B23VN12116
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 10/20/2023
Issuing Office
Valley
Current Status
Issued on 10/20/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/7/2023 APPLICANT
Assigned to Plan Check Engineer 9/13/2023 ARTIN ZARUKIAN
Corrections Issued 9/16/2023 ARTIN ZARUKIAN
Building Plans Picked Up 9/21/2023 APPLICANT
Plan Check Approved 10/19/2023 ANGELICA MARTINEZ
Issued 10/20/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/28/2023 COLIN LOREDO
Sewer availability Cleared 9/28/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 9/29/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/8/2023 Conditional Approval MORRIS JACKSON
Footing/Foundation/Slab 11/8/2023 Approved MORRIS JACKSON
Pre-Inspection 11/8/2023 Approved MORRIS JACKSON
ELECTRICAL-Rough 11/13/2023 Approved JEFFREY BULL
HVAC-Rough 11/13/2023 Approved JEFFREY BULL
PLUMBING-Rough 11/13/2023 Approved JEFFREY BULL
Underground Mechanical 11/13/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 11/15/2023 Approved JEFFREY BULL
Green Building Rough 11/15/2023 Approved JEFFREY BULL
HVAC-Rough 11/15/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 11/15/2023 Partial Approval JEFFREY BULL
Drywall Nailing 11/20/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 11/27/2023 Approved JEFFREY BULL
Final 6/1/2026 Corrections Issued JUAN ALVARADO
Green Building Final 6/1/2026 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 6/1/2026 SGSOV Not Ready JUAN ALVARADO
Smoke Detectors 6/1/2026 Approved JUAN ALVARADO
Special/Order Compliance 6/1/2026 Not Ready for Inspection JUAN ALVARADO