7944 N SALE AVE 91304

Certificate Information: 7944 N SALE AVE 91304

Application / Permit
23016-20000-29984
Plan Check / Job No.
B23VN11967
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN REMOVE AND REPLACE FIRE DAMAGED ROOF FRAMING OVER ENTIRE RESIDENCE (APPROXIMATELY 1,362 SQUARE FEET) EXCLUDING ATTACHED GARAGE. PER ENGINEERING DESIGN. NFPA 13D FIRE SPRINKLERS REQUIRED.
Permit Issued
Issued on 12/13/2023
Issuing Office
Current Status
Permit Finaled on 6/25/2024

Permit Application Status History

Submitted 9/5/2023 APPLICANT
Assigned to Plan Check Engineer 9/8/2023 ALFREDO JARA
Corrections Issued 9/9/2023 ALFREDO JARA
Plan Check Approved 11/4/2023 ALFREDO JARA
Issued 12/13/2023 APPLICANT
Permit Finaled 6/24/2024 CHRIS CHRISTENSEN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/21/2023 LEE GUILBEAUX
Low Impact Development (LID) Cleared 11/1/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 11/1/2023 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 11/1/2023 LEE GUILBEAUX

Contact Information

Contractor Vicsinc.Com; Lic. No.: 1002544-B       ,
Engineer Hansen,, Hans Christian; Lic. No.: C80546 12831 MALENA DR      SANTA ANA, CA 92705
Engineer Hansen,, Hans Christian; Lic. No.: NA80546       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 12/15/2023 Corrections Issued JEFFREY HARTLINE
Pre-Inspection 12/15/2023 Conditional Approval JEFFREY HARTLINE
Insulation 12/19/2023 Partial Approval JEFFREY HARTLINE
Interior/Exterior Lathing 12/19/2023 Not Ready for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 1/2/2024 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 1/2/2024 Partial Approval JEFFREY HARTLINE
HVAC-Rough 1/2/2024 Partial Approval JEFFREY HARTLINE
Interior/Exterior Lathing 1/2/2024 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 1/2/2024 Partial Approval JEFFREY HARTLINE
Pre-Inspection 1/2/2024 Conditional Approval JEFFREY HARTLINE
Wood Frame 1/2/2024 Not Ready for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 1/5/2024 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 1/5/2024 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 1/5/2024 Partial Approval JEFFREY HARTLINE
BUILDING-Rough-Frame 1/9/2024 Approved JEFFREY HARTLINE
Insulation 1/9/2024 Approved JEFFREY HARTLINE
Green Building Rough 1/10/2024 Approved JEFFREY HARTLINE
Drywall Nailing 1/11/2024 Approved JEFFREY HARTLINE
Final 4/1/2024 Not Ready for Inspection JEFFREY HARTLINE
Gas Test 4/1/2024 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 4/1/2024 SGSOV Approved JEFFREY HARTLINE
Service/Power Release 4/1/2024 Corrections Issued JEFFREY HARTLINE
Smoke Detectors 4/1/2024 Not Ready for Inspection JEFFREY HARTLINE
Service/Power Release 4/25/2024 Not Ready for Inspection JEFFREY HARTLINE
Final 6/24/2024 Permit Finaled CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 6/24/2024 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 6/24/2024 Approved CHRIS CHRISTENSEN