8430 S REGIS WAY 90045

Certificate Information: 8430 S REGIS WAY 90045

Application / Permit
23016-20000-29708
Plan Check / Job No.
B23VN11915
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 18' DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d). ALL WORK PER WFPP.
Permit Issued
Issued on 1/5/2024
Issuing Office
Current Status
CofO Issued on 5/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2023 APPLICANT
Assigned to Plan Check Engineer 9/8/2023 HAYATO TSUCHIYA
Corrections Issued 9/9/2023 HAYATO TSUCHIYA
Building Plans Picked Up 9/12/2023 APPLICANT
Issued 1/5/2024 APPLICANT
CofO in Progress 5/3/2024 BOBBY KEY
Permit Finaled 5/7/2024 DANIEL ORRANTE
CofO Issued 5/7/2024 DANIEL ORRANTE
Permit Finaled 5/7/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/23/2023 DARIN LAM
Sewer availability Cleared 9/23/2023 DARIN LAM
Construction near power lines Cleared 12/26/2023 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 1/4/2024 DARIN LAM
Specific Plan Cleared 1/4/2024 NELSON RODRIGUEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/24/2024 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/24/2024 Partial Approval BOBBY KEY
Footing/Foundation/Slab 1/24/2024 Approved BOBBY KEY
Green Building Rough 1/24/2024 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 2/1/2024 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 2/16/2024 Approved BOBBY KEY
Gas Test 2/16/2024 Approved BOBBY KEY
HVAC-Rough 2/16/2024 Conditional Approval BOBBY KEY
PLUMBING-Rough 2/16/2024 Conditional Approval BOBBY KEY
BUILDING-Rough-Frame 2/23/2024 Conditional Approval BOBBY KEY
Green Building Rough 2/23/2024 Approved BOBBY KEY
Interior/Exterior Lathing 2/23/2024 Partial Approval BOBBY KEY
Insulation 3/5/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 3/8/2024 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 3/8/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 3/18/2024 Approved BOBBY KEY
Interior/Exterior Lathing 3/18/2024 Approved BOBBY KEY
Rough-Elec/Plmb/HVAC 3/18/2024 Approved BOBBY KEY
Final 5/3/2024 OK to Issue CofO BOBBY KEY
Green Building Final 5/3/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/3/2024 SGSOV Approved BOBBY KEY
Smoke Detectors 5/3/2024 Approved BOBBY KEY