7503 S HOBART BLVD 90047

Certificate Information: 7503 S HOBART BLVD 90047

Application / Permit
23016-20000-29664
Plan Check / Job No.
B23VN11890
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE (E) PATIO AND PORTION OF (E) WORSHOP AND CONVERT (E) GARAGE AND REMAINING WORKSHOP PORTION TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK PER ENGINEERED DESIGN.
Permit Issued
Issued on 12/20/2023
Issuing Office
Valley
Current Status
CofO Issued on 8/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2023 APPLICANT
Assigned to Plan Check Engineer 9/8/2023 ARTIN ZARUKIAN
Corrections Issued 9/9/2023 ARTIN ZARUKIAN
Building Plans Picked Up 9/11/2023 APPLICANT
Applicant returned to address corrections 11/17/2023 ISIS ARGUETA
Plan Check Approved 12/4/2023 OMAR GARNICA
Issued 12/20/2023 APPLICANT
CofO in Progress 8/5/2024 JOSE MACIAS
CofO Issued 8/5/2024 DEROLD HAUFF
Permit Finaled 8/5/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/6/2023 ARNULFO CHAMU
Roof/Waste drainage to street Cleared 10/6/2023 ARNULFO CHAMU
Sewer availability Cleared 10/6/2023 ARNULFO CHAMU
Eng Process Fee Ord 176,300 Cleared 12/4/2023 NIKKI ZULUETA

Contact Information

Contractor Sarahang Construction Inc; Lic. No.: 897724-B 39312 DUNBAR      PALMDALE, CA 93551
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 22634 SYLVAN ST      WOODLAND HILLS, CA 91367

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/26/2024 Approved JOSE MACIAS
Footing/Foundation/Slab 3/26/2024 Partial Approval JOSE MACIAS
Footing/Foundation/Slab 3/29/2024 Partial Approval CRAIG DAVIS
BUILDING-Rough-Frame 4/22/2024 Corrections Issued JOSE MACIAS
ELECTRICAL-Rough 4/22/2024 Corrections Issued JOSE MACIAS
Green Building Rough 4/22/2024 Corrections Issued JOSE MACIAS
HVAC-Rough 4/22/2024 Approved JOSE MACIAS
PLUMBING-Rough 4/22/2024 Corrections Issued JOSE MACIAS
Sewer 4/22/2024 Not Ready for Inspection JOSE MACIAS
Deputy Drilled-In Anchors 4/26/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 4/30/2024 Approved JOSE MACIAS
ELECTRICAL-Rough 4/30/2024 Approved JOSE MACIAS
Green Building Rough 4/30/2024 Approved JOSE MACIAS
PLUMBING-Rough 4/30/2024 Approved JOSE MACIAS
Insulation 5/2/2024 Approved JOSE MACIAS
Drywall Nailing 5/7/2024 Approved JOSE MACIAS
Final 6/12/2024 Corrections Issued JOSE MACIAS
Green Building Final 6/12/2024 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 6/12/2024 SGSOV Approved JOSE MACIAS
Smoke Detectors 6/12/2024 Approved JOSE MACIAS