5260-5260 1/2 W PACKARD ST 90019
Certificate Information: 5260-5260 1/2 W PACKARD ST 90019
- Application / Permit
- 23016-20000-29623
- Plan Check / Job No.
- B23VN11864
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO (2) NEW DETACHED ADU's PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)1, (d)1, and (g). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 5/30/2024
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 3/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2023 | JESSE ARELLANO |
| Corrections Issued | 9/9/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 9/12/2023 | APPLICANT |
| Plan Check Approved | 1/25/2024 | MIROOSH KHACHATOORIAN |
| Issued | 5/30/2024 | APPLICANT |
| CofO in Progress | 3/10/2025 | ARTHUR NEGRETE |
| Permit Finaled | 3/29/2025 | DEROLD HAUFF |
| Permit Finaled | 3/29/2025 | DEROLD HAUFF |
| CofO Issued | 3/29/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/11/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2023 | WALLIE JONG |
| Sewer availability | Cleared | 9/11/2023 | WALLIE JONG |
| Construction near power lines | Cleared | 1/20/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/20/2024 | RIDWAN HARDY |
Contact Information
| Architect | Nigosian,, Michael Nickolas; Lic. No.: C35308 | 75-572 PAINTED DESERT DRIVE INDIAN WELLS, CA 92210 |
| Contractor | Wynn Builders Inc; Lic. No.: 825806-B | 409 N PACIFIC COAST HWY 511 REDONDO BEACH, CA 90277 |
| Engineer | Boranian,, Paul; Lic. No.: S5944 | 23261 BURBANK BL WOODLAND HILLS, CA 91367 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/19/2024 | Approved | ARTHUR NEGRETE |
| Underground Mechanical | 8/20/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/18/2024 | Approved | ARTHUR NEGRETE |
| Underground Mechanical | 9/18/2024 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 10/25/2024 | Corrections Issued | ARTHUR NEGRETE |
| PLUMBING-Rough | 10/25/2024 | Corrections Issued | ARTHUR NEGRETE |
| Wood Frame | 10/25/2024 | Partial Approval | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 11/6/2024 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 11/6/2024 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 11/6/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 11/6/2024 | Approved | ARTHUR NEGRETE |
| METHANE-Rough | 11/6/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 11/6/2024 | Approved | ARTHUR NEGRETE |
| Insulation | 11/14/2024 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 11/14/2024 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 11/27/2024 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 11/27/2024 | Not Ready for Inspection | ANTHONY RAMOS |
| Interior/Exterior Lathing | 12/3/2024 | Corrections Issued | JOSH MEISTER |
| Interior/Exterior Lathing | 12/6/2024 | Approved | JOSH MEISTER |
| Green Building Final | 2/27/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| PLUMBING-Final | 2/27/2025 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 2/27/2025 | SGSOV Not Ready | ARTHUR NEGRETE |
| Smoke Detectors | 2/27/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 2/28/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 2/28/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 2/28/2025 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 3/5/2025 | Approved | ARTHUR NEGRETE |
| Final | 3/7/2025 | OK to Issue CofO | ARTHUR NEGRETE |
| Green Building Final | 3/7/2025 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 3/7/2025 | SGSOV Approved | ARTHUR NEGRETE |