924 E 46TH ST 90011

Certificate Information: 924 E 46TH ST 90011

Application / Permit
23016-20000-29589
Plan Check / Job No.
B23VN11852
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT (E) GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK PER WFPP.
Permit Issued
Issued on 10/13/2023
Issuing Office
Metro
Current Status
CofO Issued on 12/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2023 APPLICANT
Assigned to Plan Check Engineer 10/2/2023 ISIS ARGUETA
Corrections Issued 10/3/2023 ISIS ARGUETA
Plan Check Approved 10/13/2023 NEHEMIAS RAMOS
Issued 10/13/2023 APPLICANT
CofO in Progress 12/2/2025 ALEJANDRO DE ARTOLA
Permit Finaled 12/4/2025 DEROLD HAUFF
CofO Issued 12/4/2025 DEROLD HAUFF
Permit Finaled 12/4/2025 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 10/6/2023 AMBER CAMPBELL
Address approval Cleared 10/12/2023 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 10/12/2023 AMBER CAMPBELL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/22/2024 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 6/24/2024 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 7/8/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 7/26/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 7/30/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 8/9/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 9/9/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/1/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/1/2024 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 10/1/2024 Approved ALEJANDRO DE ARTOLA
Wood Frame 10/1/2024 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 10/9/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 10/11/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/11/2024 Approved ALEJANDRO DE ARTOLA
Wood Frame 10/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 10/16/2024 Approved MICHAEL LEWIS
Insulation 10/18/2024 Approved JOSH MEISTER
Drywall Nailing 12/16/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/16/2024 Partial Approval ALEJANDRO DE ARTOLA
Pre-Inspection 7/2/2025 Not Ready for Inspection JOHN QUINTANILLA
Pre-Inspection 7/10/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 7/11/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 11/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 11/12/2025 Approved ALEJANDRO DE ARTOLA
Green Building Final 11/12/2025 Approved ALEJANDRO DE ARTOLA
Green Building Rough 11/12/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 11/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 11/12/2025 SGSOV Not Ready ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/1/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/1/2025 Approved ALEJANDRO DE ARTOLA
Final 12/1/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 12/1/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 12/1/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/1/2025 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 12/1/2025 Approved ALEJANDRO DE ARTOLA
Final 12/2/2025 OK to Issue CofO ALEJANDRO DE ARTOLA
PLUMBING-Final 12/2/2025 Approved ALEJANDRO DE ARTOLA