6864 N RANCHITO AVE 91405
Certificate Information: 6864 N RANCHITO AVE 91405
- Application / Permit
- 23016-20000-29181
- Plan Check / Job No.
- B23VN11681
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF AN EXISTING 40'-0" x 20'-0" UNPERMITTED STRUCTURE BUILT PRIOR TO JAN 1, 2018 TO AN ACCESSORY DWELLING UNIT PER GOVT. CODE SECTION 65852.23. NEW 5' X 20' ADDITION TO THE (N) ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 8/1/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 9/4/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 9/7/2023 | APPLICANT |
| Plan Check Approved | 8/1/2024 | GIOVANNY CHAVEZ |
| Issued | 8/1/2024 | APPLICANT |
| CofO in Progress | 7/10/2025 | RYAN SALAZAR |
| Permit Finaled | 7/29/2025 | RUBEN SALAS |
| CofO Issued | 7/29/2025 | RUBEN SALAS |
| Permit Finaled | 7/29/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/17/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2023 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 10/17/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 10/17/2023 | COLIN LOREDO |
| Miscellaneous | Cleared | 6/17/2024 | DORIAN AGUILAR |
| Construction near power lines | Cleared | 7/5/2024 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/19/2024 | Partial Approval | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 11/20/2024 | Conditional Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 11/25/2024 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 11/25/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 1/7/2025 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 2/21/2025 | Conditional Approval | RYAN SALAZAR |
| PLUMBING-Rough | 2/21/2025 | Approved | RYAN SALAZAR |
| Insulation | 2/25/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 3/5/2025 | Approved | RYAN SALAZAR |
| Gas Test | 3/5/2025 | Corrections Issued | RYAN SALAZAR |
| Green Building Rough | 3/5/2025 | Approved | RYAN SALAZAR |
| Gas Test | 3/11/2025 | Approved | RYAN SALAZAR |
| Gas Test | 3/13/2025 | Approved | RYAN SALAZAR |
| Service/Power Release | 3/13/2025 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Final | 4/17/2025 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/16/2025 | Approved | RYAN SALAZAR |
| Final | 5/16/2025 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 5/16/2025 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 5/16/2025 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 5/16/2025 | Approved | RYAN SALAZAR |
| Final | 5/30/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 5/30/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 7/10/2025 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 7/10/2025 | Approved | RYAN SALAZAR |
| Service/Power Release | 7/10/2025 | Approved | RYAN SALAZAR |