6339 1/2 N DENNY AVE 91606
Certificate Information: 6339 1/2 N DENNY AVE 91606
- Application / Permit
- 23016-20000-29167
- Plan Check / Job No.
- B23VN11667
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED REC ROOM TO ACCESSORY DWELLING UNIT (364 SQ FT) PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 1/23/2024
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 3/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 9/5/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 9/8/2023 | APPLICANT |
| Issued | 1/23/2024 | APPLICANT |
| CofO in Progress | 2/19/2025 | JOSE AVILA |
| CofO Issued-Status Void | 3/13/2025 | RUBEN SALAS |
| Permit Finaled-Status Void | 3/13/2025 | RUBEN SALAS |
| Re-Activate Permit | 3/27/2025 | RUBEN SALAS |
| Permit Finaled | 3/27/2025 | RUBEN SALAS |
| CofO Corrected | 3/27/2025 | RUBEN SALAS |
| Permit Finaled | 3/27/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/26/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 9/26/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2023 | NIKKI ZULUETA |
| Construction near power lines | Cleared | 1/18/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/19/2024 | Approved | JOSE AVILA |
| Special/Order Compliance | 4/19/2024 | Corrections Issued | JOSE AVILA |
| Wood Frame | 9/16/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 9/23/2024 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 9/23/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 9/23/2024 | Corrections Issued | JOSE AVILA |
| Wood Frame | 9/23/2024 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 10/15/2024 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 10/15/2024 | Approved | JOSE AVILA |
| Green Building Rough | 10/15/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 10/15/2024 | Approved | JOSE AVILA |
| Insulation | 10/15/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 10/15/2024 | Approved | JOSE AVILA |
| Final | 1/29/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 1/29/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/29/2025 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 1/29/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Drywall Nailing | 2/11/2025 | Approved | JOSE AVILA |
| Insulation | 2/11/2025 | Approved | JOSE AVILA |
| Gas Test | 2/14/2025 | Approved | JOSE AVILA |
| Final | 2/18/2025 | OK to Issue CofO | JOSE AVILA |
| Green Building Final | 2/18/2025 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/18/2025 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 2/18/2025 | Approved | JOSE AVILA |
| Service/Power Release | 2/24/2025 | Approved | JOSE AVILA |