10122-10124 N COZYCROFT AVE 91311

Certificate Information: 10122-10124 N COZYCROFT AVE 91311

Application / Permit
23016-20000-28881
Plan Check / Job No.
B23VN11576
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan Convert attached garage to ADU per state law and GCS65852.2(e)(1)(A).
Permit Issued
Issued on 11/22/2023
Issuing Office
Current Status
CofO Issued on 5/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/30/2023 APPLICANT
Assigned to Plan Check Engineer 9/5/2023 JOSEPH RAFOLS
Corrections Issued 9/6/2023 JOSEPH RAFOLS
Applicant returned to address corrections 10/7/2023 MINA HABILI
Applicant returned to address corrections 10/20/2023 MINA HABILI
Plan Check Approved 10/24/2023 ZAW HAN
Issued 11/22/2023 APPLICANT
CofO in Progress 5/15/2024 DAVID SCANTLIN
CofO in Progress 5/16/2024 DAVID SCANTLIN
CofO in Progress 5/17/2024 DAVID SCANTLIN
Permit Finaled 5/17/2024 JOHN JANSON
CofO Issued 5/17/2024 JOHN JANSON
Permit Finaled 5/17/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/7/2023 TAL SHEMEN
Sewer availability Cleared 9/7/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 9/11/2023 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/8/2024 Approved DAVID SCANTLIN
Footing/Foundation/Slab 1/8/2024 Approved DAVID SCANTLIN
PLUMBING-Rough 1/8/2024 Partial Approval DAVID SCANTLIN
Deputy Drilled-In Anchors 1/19/2024 Conditional Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 1/22/2024 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 1/26/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 1/26/2024 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 1/26/2024 Approved DAVID SCANTLIN
Shower Pan 1/26/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 1/30/2024 Approved DAVID SCANTLIN
Green Building Rough 1/30/2024 Approved DAVID SCANTLIN
HVAC-Rough 1/30/2024 Approved DAVID SCANTLIN
Insulation 1/30/2024 Approved DAVID SCANTLIN
Drywall Nailing 2/1/2024 Approved DAVID SCANTLIN
ELECTRICAL-Final 4/9/2024 Not Ready for Inspection DAVID SCANTLIN
Service/Power Release 4/9/2024 Approved DAVID SCANTLIN
Final 5/6/2024 Corrections Issued DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 5/6/2024 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 5/6/2024 Approved DAVID SCANTLIN
Final 5/14/2024 OK to Issue CofO DAVID SCANTLIN
Service/Power Release 5/16/2024 Approved DAVID SCANTLIN