5428 N PENFIELD AVE 91364
Certificate Information: 5428 N PENFIELD AVE 91364
- Application / Permit
- 23016-20000-28596
- Plan Check / Job No.
- B23VN11438
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DET GARAGE TO ADU PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/18/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2023 | JESSE ARELLANO |
| Corrections Issued | 9/1/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 9/5/2023 | APPLICANT |
| Plan Check Approved | 9/18/2023 | ISIS ARGUETA |
| Issued | 9/18/2023 | APPLICANT |
| CofO in Progress | 12/21/2023 | JOHN KIDWELL |
| Permit Finaled | 12/27/2023 | JOHN JANSON |
| CofO Issued | 12/27/2023 | JOHN JANSON |
| Permit Finaled | 12/27/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/6/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 9/6/2023 | TAL SHEMEN |
| ZA Case | Cleared | 9/11/2023 | NELSON RODRIGUEZ |
| Grading Pre-Inspection | Cleared | 9/15/2023 | MICHAEL TEMPLE |
Contact Information
| Contractor | Trig Builders Inc; Lic. No.: 1030887-B | 6442 COLDWATER CANYON AVE 111 NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/3/2023 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 10/3/2023 | Approved | PETER FOLLING |
| Sewer | 10/3/2023 | Approved | PETER FOLLING |
| Deputy Drilled-In Anchors | 10/4/2023 | No Access for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 10/10/2023 | Corrections Issued | PETER FOLLING |
| Deputy Drilled-In Anchors | 10/11/2023 | No Access for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 10/13/2023 | Approved | PETER FOLLING |
| ELECTRICAL-Rough | 10/26/2023 | Corrections Issued | PETER FOLLING |
| HVAC-Rough | 10/26/2023 | Approved | PETER FOLLING |
| PLUMBING-Rough | 10/26/2023 | Approved | PETER FOLLING |
| ELECTRICAL-Rough | 11/3/2023 | Partial Inspection | MORRIS JACKSON |
| Interior/Exterior Lathing | 11/3/2023 | Partial Approval | MORRIS JACKSON |
| Shower Pan | 11/3/2023 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 11/15/2023 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2023 | Approved | PETER FOLLING |
| Green Building Rough | 11/15/2023 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 11/17/2023 | Approved | SEAN HAUPT |
| Green Building Rough | 11/17/2023 | Approved | SEAN HAUPT |
| Insulation | 11/17/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 11/17/2023 | Approved | SEAN HAUPT |
| Drywall Nailing | 11/21/2023 | Approved | ALEXANDER HANDY |
| Final | 12/12/2023 | Corrections Issued | JOHN KIDWELL |
| Green Building Final | 12/12/2023 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 12/12/2023 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 12/12/2023 | Approved | JOHN KIDWELL |
| Final | 12/20/2023 | OK to Issue CofO | JOHN KIDWELL |
| Green Building Final | 12/20/2023 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 12/20/2023 | SGSOV Approved | JOHN KIDWELL |