15143 W SUTTON ST 91403
Certificate Information: 15143 W SUTTON ST 91403
- Application / Permit
- 23016-20000-28482
- Plan Check / Job No.
- B23VN11382
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE AND ALQ TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/8/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2023 | SERGIO MUNIZ |
| Corrections Issued | 8/31/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 9/1/2023 | APPLICANT |
| Issued | 9/8/2023 | APPLICANT |
| CofO in Progress | 8/27/2024 | JACK KARGODORIAN |
| Permit Finaled | 8/31/2024 | DANIEL ORRANTE |
| CofO Issued | 8/31/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/31/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/5/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 9/5/2023 | MEGAN GODINEZ |
| ZA Case | Cleared | 9/5/2023 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2023 | ROMAN GUTIERREZ |
| Grading Pre-Inspection | Cleared | 9/8/2023 | SERGIO MUNIZ |
Contact Information
| Contractor | D K R Construction Inc; Lic. No.: 1070450-B | 7110 FOREST HILLS RD WEST HILLS, CA 91307 |
| Engineer | Sin,, John Paul; Lic. No.: C91162 | 122 N GRAMERCY PL LOS ANGELES, CA 90004 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/16/2024 | Conditional Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 4/17/2024 | Conditional Approval | DAVID MATSON |
| PLUMBING-Rough | 5/6/2024 | Partial Approval | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 5/22/2024 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2024 | Partial Approval | JACK KARGODORIAN |
| Insulation | 6/5/2024 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 6/5/2024 | Not Ready for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 6/11/2024 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2024 | Approved | JACK KARGODORIAN |
| Green Building Rough | 6/11/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/11/2024 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 6/17/2024 | Approved | STUART CHAPMAN |
| Shower Pan | 6/17/2024 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 7/1/2024 | Partial Approval | JACK KARGODORIAN |
| Final | 8/22/2024 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 8/22/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 8/22/2024 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 8/22/2024 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 8/26/2024 | Approved | JACK KARGODORIAN |
| Final | 8/26/2024 | OK to Issue CofO | JACK KARGODORIAN |
| Green Building Final | 8/26/2024 | Approved | JACK KARGODORIAN |
| HVAC-Final | 8/26/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 8/26/2024 | Approved | JACK KARGODORIAN |