8211-8213 N WISNER AVE 91402
Certificate Information: 8211-8213 N WISNER AVE 91402
- Application / Permit
- 23016-20000-28475
- Plan Check / Job No.
- B23VN11380
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATT. GARAGE & SUNROOM TO JR ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) and 65852.229
- Permit Issued
- Issued on 11/13/2023
- Issuing Office
- Current Status
- CofO Issued on 8/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2023 | SERGIO MUNIZ |
| Corrections Issued | 8/31/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 9/1/2023 | APPLICANT |
| Issued | 11/13/2023 | APPLICANT |
| CofO in Progress | 8/16/2024 | VINCENT HANLEY |
| CofO Issued | 8/28/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/28/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/9/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/9/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/18/2024 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 3/27/2024 | Approved | KIRK SANDERS |
| Sewer | 3/27/2024 | Approved | KIRK SANDERS |
| Underground Mechanical | 3/27/2024 | Partial Approval | KIRK SANDERS |
| Deputy Drilled-In Anchors | 3/28/2024 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 5/20/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 5/20/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 5/20/2024 | Corrections Issued | VINCENT HANLEY |
| Shower Pan | 5/20/2024 | Approved | VINCENT HANLEY |
| Insulation | 5/29/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 5/29/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 6/11/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/11/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/11/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 8/6/2024 | Approved | VINCENT HANLEY |
| Final | 8/6/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 8/6/2024 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 8/6/2024 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 8/6/2024 | Approved | VINCENT HANLEY |
| Final | 8/13/2024 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 8/13/2024 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 8/15/2024 | Approved | VINCENT HANLEY |
| Final | 8/15/2024 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 8/15/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 8/15/2024 | Approved | VINCENT HANLEY |