22106 W CLARENDON ST 91367

Certificate Information: 22106 W CLARENDON ST 91367

Application / Permit
23016-20000-28018
Plan Check / Job No.
B23VN11233
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
eplan New tenant improvement to an existing office space and facade renovation
Permit Issued
Issued on 9/20/2024
Issuing Office
Current Status
Permit Finaled on 5/2/2025

Permit Application Status History

Submitted 8/24/2023 APPLICANT
Assigned to Plan Check Engineer 9/7/2023 ARSALAN SHABESTARI
Corrections Issued 9/12/2023 ARSALAN SHABESTARI
Quality Review Completed 9/15/2023 GARO TELMI
Plan Check Approved 8/9/2024 ARSALAN SHABESTARI
Issued 9/20/2024 APPLICANT
Permit Finaled 5/1/2025 BRIAN KELLY

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/6/2023 COLIN LOREDO
Roof/Waste drainage to street Cleared 12/6/2023 COLIN LOREDO
Miscellaneous Cleared 12/7/2023 NATHAN ROMINE
ZA Case Cleared 12/7/2023 NATHAN ROMINE
ZA Case Cleared 12/7/2023 NATHAN ROMINE
Grading Pre-Inspection Cleared 12/15/2023 ROBERT PINA
DAS Clearance Cleared 2/5/2024 Pinank Patel
Specific Plan Cleared 7/23/2024 BRENNEN OBETO

Contact Information

Architect Maio,, Miguel J; Lic. No.: NA27923       ,
Contractor J R Development Inc; Lic. No.: 561978-B       ,
Contractor Mercury Construction; Lic. No.: 561978-B       ,

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/17/2024 Conditional Approval BRIAN KELLY
Wood Frame 10/23/2024 Not Ready for Inspection BRIAN KELLY
Excavation/Setback/Form/Re-Bar 10/30/2024 Approved BRIAN KELLY
Deputy Reinf. Concrete 10/31/2024 Conditional Approval BRIAN KELLY
Wood Frame 10/31/2024 Not Ready for Inspection BRIAN KELLY
Reinforced Masonry Frame 11/6/2024 Not Ready for Inspection BRIAN KELLY
Reinforced Masonry Frame 11/8/2024 Partial Approval BRIAN KELLY
Reinforced Masonry Frame 11/15/2024 Approved BRIAN KELLY
Deputy Reinf. Masonry 11/18/2024 Conditional Approval BRIAN KELLY
Reinforced Masonry Frame 11/19/2024 Approved BRIAN KELLY
Floor/Roof Diaphrgm/Shear Wall 11/26/2024 Partial Approval BRIAN KELLY
Wood Frame 1/23/2025 Partial Approval BRIAN KELLY
Drywall Nailing 1/29/2025 Partial Inspection BRIAN KELLY
Wood Frame 2/5/2025 Approved BRIAN KELLY
Insulation 2/7/2025 Approved BRIAN KELLY
Interior/Exterior Lathing 2/21/2025 Approved KENNETH ROBERTS
Drywall Nailing 2/24/2025 Approved BRIAN KELLY
Final 4/18/2025 Not Ready for Inspection BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 4/18/2025 SGSOV Not Ready BRIAN KELLY
Smoke Detectors 4/18/2025 Not Ready for Inspection BRIAN KELLY
Final 5/1/2025 Permit Finaled BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 5/1/2025 SGSOV Approved BRIAN KELLY
Smoke Detectors 5/1/2025 Approved BRIAN KELLY