20146-20148 W ACRE ST 91306

Certificate Information: 20146-20148 W ACRE ST 91306

Application / Permit
23016-20000-27775
Plan Check / Job No.
B23VN11107
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. Convert (E) Garage to a Junior Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A) and 65852.22 and WFPP
Permit Issued
Issued on 10/2/2023
Issuing Office
Current Status
CofO Issued on 2/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2023 APPLICANT
Assigned to Plan Check Engineer 8/22/2023 AMY GUEVARRA
Corrections Issued 8/23/2023 AMY GUEVARRA
Plan Check Approved 9/28/2023 AMY GUEVARRA
Issued 10/2/2023 APPLICANT
CofO in Progress 2/18/2026 JEFFREY HARTLINE
Permit Finaled 2/23/2026 JOHN JANSON
CofO Issued 2/23/2026 JOHN JANSON
Permit Finaled 2/23/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/26/2023 CARLOS AGUILERA
Sewer availability Cleared 8/26/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/28/2023 CARLOS AGUILERA

Contact Information

Contractor United Construction Group Inc; Lic. No.: 1077065-B       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/10/2023 Approved JEFFREY HARTLINE
PLUMBING-Rough 10/10/2023 Approved JEFFREY HARTLINE
Sewer 10/17/2023 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 11/2/2023 Corrections Issued JEFFREY HARTLINE
ELECTRICAL-Rough 11/2/2023 Approved JEFFREY HARTLINE
HVAC-Rough 11/2/2023 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 11/2/2023 Approved JEFFREY HARTLINE
PLUMBING-Rough 11/2/2023 Approved JEFFREY HARTLINE
Shower Pan 11/2/2023 Approved JEFFREY HARTLINE
HVAC-Rough 11/6/2023 Approved JEFFREY HARTLINE
Wood Frame 11/6/2023 Approved JEFFREY HARTLINE
Insulation 11/8/2023 Approved JEFFREY HARTLINE
Drywall Nailing 11/13/2023 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 11/13/2023 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 2/1/2024 Approved JEFFREY HARTLINE
Final 2/1/2024 Corrections Issued JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 2/1/2024 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 2/1/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Final 2/17/2026 Approved JEFFREY HARTLINE
Final 2/17/2026 OK to Issue CofO JEFFREY HARTLINE
HVAC-Final 2/17/2026 Approved JEFFREY HARTLINE
PLUMBING-Final 2/17/2026 Approved JEFFREY HARTLINE