8165 N WILKINSON AVE 91606
Certificate Information: 8165 N WILKINSON AVE 91606
- Application / Permit
- 23016-20000-27582
- Plan Check / Job No.
- B23VN11001
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED REC ROOM TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 12/12/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 8/19/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 8/23/2023 | APPLICANT |
| Plan Check Approved | 12/12/2023 | ALEC MOUSAKHANIAN |
| Issued | 12/12/2023 | APPLICANT |
| CofO in Progress | 4/10/2024 | MATTHEW NELSON |
| Permit Finaled | 4/13/2024 | RUBEN SALAS |
| CofO Issued | 4/13/2024 | RUBEN SALAS |
| Permit Finaled | 4/13/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/28/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 8/28/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 2/23/2024 | Corrections Issued | MATTHEW NELSON |
| Final | 2/23/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 2/23/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 2/23/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 2/23/2024 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 2/23/2024 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/9/2024 | Approved | MATTHEW NELSON |
| Final | 4/9/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 4/9/2024 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 4/9/2024 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 4/9/2024 | Approved | MATTHEW NELSON |
| Final | 4/10/2024 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 4/10/2024 | Approved | MATTHEW NELSON |
| Service/Power Release | 4/10/2024 | Approved | MATTHEW NELSON |