5750 N WILHELMINA AVE 91367

Certificate Information: 5750 N WILHELMINA AVE 91367

Application / Permit
23016-20000-27537
Plan Check / Job No.
B23VN09942
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*eplan* 82 SQ.FT CONVERSION OF EXISTING ENTRY PORCH TO THE EXISTING HOUSE, INTO NEW OFFICE / GAME ROOM. REMOVE CLOSET OF BEDROOM # 3 AND BUILD NEW BATHROOM TO ACCESS FROM HALLWAY. ALL WORK DONE PER ENGINEER
Permit Issued
Issued on 10/24/2023
Issuing Office
Current Status
Permit Finaled on 12/24/2024

Permit Application Status History

Submitted 7/27/2023 APPLICANT
Assigned to Plan Check Engineer 8/10/2023 NAREG ATARIAN
Corrections Issued 8/16/2023 NAREG ATARIAN
Quality Review Completed 8/24/2023 OMID HEDAYAT
Applicant returned to address corrections 10/12/2023 NAREG ATARIAN
Applicant returned to address corrections 10/19/2023 NAREG ATARIAN
Plan Check Approved 10/23/2023 NAREG ATARIAN
Issued 10/24/2023 APPLICANT
Permit Finaled 12/23/2024 TROY SANDERS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/19/2023 NAREG ATARIAN

Contact Information

Contractor Oak Development The; Lic. No.: 1094201-B       ,
Contractor The Oak Development; Lic. No.: 1094201-B       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/16/2023 Conditional Approval TROY SANDERS
Footing/Foundation/Slab 11/20/2023 Approved TROY SANDERS
BUILDING-Rough-Frame 12/15/2023 Approved TROY SANDERS
ELECTRICAL-Rough 12/15/2023 Approved TROY SANDERS
Green Building Rough 12/15/2023 Not Ready for Inspection TROY SANDERS
HVAC-Rough 12/15/2023 Approved TROY SANDERS
PLUMBING-Rough 12/15/2023 Approved TROY SANDERS
BUILDING-Rough-Frame 12/22/2023 Approved TROY SANDERS
Green Building Rough 12/22/2023 Approved TROY SANDERS
Insulation 12/22/2023 Approved TROY SANDERS
Interior/Exterior Lathing 12/22/2023 Partial Approval TROY SANDERS
Drywall Nailing 12/28/2023 Approved TROY SANDERS
ELECTRICAL-Rough 5/24/2024 Approved TROY SANDERS
PLUMBING-Rough 5/24/2024 Approved TROY SANDERS
Interior/Exterior Lathing 5/31/2024 Partial Approval TROY SANDERS
Shower Pan 5/31/2024 Approved TROY SANDERS
Final 12/23/2024 Permit Finaled TROY SANDERS
Green Building Final 12/23/2024 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 12/23/2024 SGSOV Approved TROY SANDERS
Smoke Detectors 12/23/2024 Approved TROY SANDERS