4413-4415 3/4 N TUJUNGA AVE 91602
Certificate Information: 4413-4415 3/4 N TUJUNGA AVE 91602
- Application / Permit
- 23016-20000-27194
- Plan Check / Job No.
- B23VN10864
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePlan. Conversion of (E) attached 4-car Garage to an Accessory Dwelling Unit per GCS 65852.2(e)(1)(c). All work per engineered plans.
- Permit Issued
- Issued on 11/27/2023
- Issuing Office
- Current Status
- CofO Issued on 7/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2023 | ZAW HAN |
| Corrections Issued | 8/22/2023 | ZAW HAN |
| Plan Check Approved | 9/29/2023 | MICHAEL LANZONE |
| Issued | 11/27/2023 | APPLICANT |
| CofO in Progress | 6/28/2024 | ROBERT DAVIS |
| Permit Finaled | 7/1/2024 | JEFFREY DURAN |
| CofO Issued | 7/1/2024 | JEFFREY DURAN |
| Permit Finaled | 7/1/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| ZI | Cleared | 8/24/2023 | RUBEN VASQUEZ |
| Address approval | Cleared | 8/29/2023 | CARLOS AGUILERA |
| Highway dedication | Cleared | 8/29/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/29/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/29/2023 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 8/30/2023 | ANDREW SANTIAGO |
| Tenant Habitability Plan | Cleared | 9/1/2023 | ISMAEL HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/5/2023 | CARLOS AGUILERA |
Contact Information
| Architect | Suayan,, Rey D; Lic. No.: NA37726 | , |
| Contractor | Rent Ready Construction Inc; Lic. No.: 1065376-B | 526 W ARBOR VITAE STREET INGLEWOOD, CA 90310 |
| Engineer | Mourad,, Daniel; Lic. No.: NA83387 | , |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/15/2023 | Conditional Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 12/18/2023 | Approved | ROBERT DAVIS |
| Wood Frame | 1/31/2024 | Approved | ANDREW DORSO |
| Insulation | 2/6/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Interior/Exterior Lathing | 2/6/2024 | Partial Approval | ROBERT DAVIS |
| Insulation | 2/9/2024 | Approved | ROBERT DAVIS |
| Interior/Exterior Lathing | 2/9/2024 | Approved | ROBERT DAVIS |
| Drywall Nailing | 2/12/2024 | Approved | DANNY RODRIGUEZ |
| Final | 4/25/2024 | OK to Issue CofO | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 4/25/2024 | SGSOV Approved | ROBERT DAVIS |