7823 W MULHOLLAND DR 90046

Certificate Information: 7823 W MULHOLLAND DR 90046

Application / Permit
23016-20000-26412
Plan Check / Job No.
B23VN10585
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED INT & EXT REMODEL TO EXISTING ONE STORY SFD W/ ATT GARAGE - REMODEL BEDRMS/BATHRMS/KITCHEN/LAUNDRY RM/LIVING RM/FAMILY RM PER PLAN. CONVERT EXISTING GARAGE INTO CARPORT BY REMOVING EX DOORS AT FRONT & REAR TO CREATE TWO OPENINGS. REMOVE & REPLACE ALL DOORS & WINDOWS. REMODEL ENTRYWAY TO ADD 7' X 10'TRELLIS ROOF TO (E) OPEN PORTION OF ROOF. WORK PER ENGINEERED DESIGN.
Permit Issued
Issued on 4/9/2024
Issuing Office
Valley
Current Status
Issued on 4/9/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/8/2023 APPLICANT
Assigned to Plan Check Engineer 8/11/2023 HAYATO TSUCHIYA
Corrections Issued 8/12/2023 HAYATO TSUCHIYA
Building Plans Picked Up 8/23/2023 APPLICANT
Applicant returned to address corrections 3/21/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 4/8/2024 OMAR GARNICA
Issued 4/9/2024 APPLICANT

Permit Application Clearance Information

Specific Plan Cleared 1/22/2024 TIFFANY CORRALES
Grading Pre-Inspection Cleared 3/28/2024 MANUEL TEJADA

Contact Information

Architect Hoffman,, Fred; Lic. No.: C8128 11558 KLING STREET      NORTH HOLLYWOOD, CA 91602
Contractor Hugs Construction; Lic. No.: 676959-B 4820 GENTRY AVENUE      VALLEY VILLAGE, CA 91607
Engineer Mourad,, Daniel; Lic. No.: C83387 542 N FULLER AVE      LOS ANGELES, CA 90036

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/15/2024 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 6/3/2024 Partial Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 7/22/2024 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/25/2024 Partial Approval BRENDAN MORELLI
ELECTRICAL-Rough 8/6/2024 Partial Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 8/8/2024 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 9/4/2024 Approved BRIAN SULLIVAN
Deputy Drilled-In Anchors 2/3/2025 Conditional Approval BRIAN SULLIVAN
Pre-Inspection 4/4/2025 Approved BRENDAN MORELLI
Deputy Drilled-In Anchors 5/5/2025 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2025 Partial Approval BRIAN SULLIVAN
Gas Test 6/3/2025 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 6/3/2025 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 9/19/2025 Approved BRIAN SULLIVAN
Shower Pan 10/27/2025 Approved ROY SPAULDING
ELECTRICAL-Rough 12/4/2025 Partial Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 12/11/2025 Partial Inspection BRIAN SULLIVAN
ELECTRICAL-Final 2/23/2026 Approved DAVID WILLIAMS
HVAC-Final 2/23/2026 Approved DAVID WILLIAMS
PLUMBING-Final 2/23/2026 Approved DAVID WILLIAMS
ELECTRICAL-Rough 4/2/2026 Approved ROY SPAULDING
HVAC-Rough 5/20/2026 Approved ROY SPAULDING
ELECTRICAL-Rough 6/10/2026 Partial Inspection ROY SPAULDING
Interior/Exterior Lathing 7/8/2026 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 7/22/2026 Approved ROY SPAULDING