17352 W LOS ALIMOS ST 91344

Certificate Information: 17352 W LOS ALIMOS ST 91344

Application / Permit
23016-20000-26334
Plan Check / Job No.
B23VN10550
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 21'-0" X 21'-0" DETACHED GARAGE TO ACCESSORY DWELLLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 8/21/2023
Issuing Office
Current Status
CofO Issued on 6/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/7/2023 APPLICANT
Assigned to Plan Check Engineer 8/11/2023 ARTIN ZARUKIAN
Corrections Issued 8/12/2023 ARTIN ZARUKIAN
Issued 8/21/2023 APPLICANT
CofO in Progress 6/18/2024 STEVEN BACK
Permit Finaled 6/26/2024 JOHN JANSON
CofO Issued 6/26/2024 JOHN JANSON
Permit Finaled 6/26/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/17/2023 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 8/17/2023 FERNANDO GIL
Sewer availability Cleared 8/17/2023 FERNANDO GIL
Construction near power lines Cleared 8/18/2023 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/16/2023 Approved HENRY KIM
PLUMBING-Rough 11/1/2023 Corrections Issued STEVEN BACK
PLUMBING-Rough 11/3/2023 Partial Approval STEVEN BACK
Sewer 11/3/2023 Approved STEVEN BACK
Deputy Drilled-In Anchors 11/28/2023 Conditional Approval STEVEN BACK
Footing/Foundation/Slab 12/7/2023 Approved STEVEN BACK
ELECTRICAL-Rough 12/19/2023 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 1/3/2024 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 1/3/2024 Approved STEVEN BACK
HVAC-Rough 1/3/2024 Corrections Issued STEVEN BACK
HVAC-Rough 1/30/2024 Not Ready for Inspection STEVEN BACK
HVAC-Rough 3/12/2024 Approved STEVEN BACK
BUILDING-Rough-Frame 3/15/2024 Approved STEVEN BACK
Green Building Rough 3/15/2024 Approved STEVEN BACK
Interior/Exterior Lathing 3/15/2024 Partial Approval STEVEN BACK
PLUMBING-Rough 3/15/2024 Approved STEVEN BACK
Insulation 4/1/2024 Approved HENRY KIM
Drywall Nailing 4/8/2024 Approved HENRY KIM
Green Building Final 4/8/2024 Partial Approval HENRY KIM
Interior/Exterior Lathing 4/12/2024 Approved HENRY KIM
ELECTRICAL-Final 6/12/2024 Approved STEVEN BACK
Final 6/12/2024 Corrections Issued STEVEN BACK
Green Building Final 6/12/2024 Approved STEVEN BACK
HVAC-Final 6/12/2024 Approved STEVEN BACK
PLUMBING-Final 6/12/2024 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/12/2024 SGSOV Not Ready STEVEN BACK
Smoke Detectors 6/12/2024 Approved STEVEN BACK
Final 6/18/2024 OK to Issue CofO STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/18/2024 SGSOV Approved STEVEN BACK
Service/Power Release 6/18/2024 Approved STEVEN BACK