20215 W LASSEN ST 91311
Certificate Information: 20215 W LASSEN ST 91311
- Application / Permit
- 23016-20000-26177
- Plan Check / Job No.
- B23VN10500
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 9/12/2023
- Issuing Office
- Current Status
- CofO Issued on 1/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/10/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 8/10/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 9/12/2023 | ROSENDO MEDINA |
| Issued | 9/12/2023 | APPLICANT |
| CofO in Progress | 1/16/2024 | DAVID SCANTLIN |
| Permit Finaled | 1/30/2024 | JOHN JANSON |
| CofO Issued | 1/30/2024 | JOHN JANSON |
| Permit Finaled | 1/30/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/18/2023 | COLIN LOREDO |
| Construction near power lines | Cleared | 8/18/2023 | WALTER RAMIREZ |
| Construction within easement | Cleared | 8/18/2023 | WALTER RAMIREZ |
| Roof/Waste drainage to street | Cleared | 8/18/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 8/18/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/22/2023 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 9/25/2023 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 9/25/2023 | Approved | DAVID SCANTLIN |
| Pre-Inspection | 9/25/2023 | Approved | DAVID SCANTLIN |
| Deputy Wood Construction | 10/5/2023 | Conditional Approval | DAVID SCANTLIN |
| ELECTRICAL-Rough | 10/5/2023 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 10/5/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 10/5/2023 | Approved | DAVID SCANTLIN |
| Sewer | 10/5/2023 | Approved | DAVID SCANTLIN |
| Wood Frame | 10/5/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 10/10/2023 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2023 | Approved | JOHN KIDWELL |
| Green Building Rough | 10/10/2023 | Approved | JOHN KIDWELL |
| Insulation | 10/10/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 10/10/2023 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 10/16/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 10/16/2023 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Final | 12/14/2023 | Approved | DAVID SCANTLIN |
| Final | 12/14/2023 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 12/14/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Final | 12/14/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 12/14/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 12/14/2023 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 12/14/2023 | Approved | DAVID SCANTLIN |
| Final | 1/16/2024 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 1/16/2024 | Approved | DAVID SCANTLIN |