1831 S CIMARRON ST 90019
Certificate Information: 1831 S CIMARRON ST 90019
- Application / Permit
- 23016-20000-25783
- Plan Check / Job No.
- B23VN10335
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 19'-6" X 18'-9" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 6/10/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 8/8/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 8/11/2023 | APPLICANT |
| Plan Check Approved | 1/26/2024 | JESSE ARELLANO |
| Issued | 6/10/2024 | APPLICANT |
| CofO in Progress | 3/11/2025 | WILLIAM SIERRA |
| Permit Finaled | 3/12/2025 | DEROLD HAUFF |
| CofO Issued | 3/12/2025 | DEROLD HAUFF |
| Permit Finaled | 3/12/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2023 | CELINA MORENO |
| Sewer availability | Cleared | 10/21/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2023 | CELINA MORENO |
| ZI | Cleared | 11/27/2023 | NELSON RODRIGUEZ |
| Construction near power lines | Cleared | 1/9/2024 | RIDWAN HARDY |
| Community Plan Implem. Overlay | Cleared | 1/23/2024 | MANERI ROMAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/17/2024 | Partial Approval | JOSEPH MCGARRY |
| Underground Mechanical | 8/2/2024 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 8/6/2024 | Corrections Issued | WILLIAM SIERRA |
| Footing/Foundation/Slab | 8/6/2024 | Partial Approval | WILLIAM SIERRA |
| Wood Frame | 8/6/2024 | Partial Approval | WILLIAM SIERRA |
| ELECTRICAL-Rough | 8/19/2024 | Partial Approval | WILLIAM SIERRA |
| PLUMBING-Rough | 8/19/2024 | Partial Approval | WILLIAM SIERRA |
| ELECTRICAL-Rough | 8/30/2024 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Partial Approval | WILLIAM SIERRA |
| Insulation | 8/30/2024 | Partial Approval | WILLIAM SIERRA |
| PLUMBING-Rough | 8/30/2024 | Approved | WILLIAM SIERRA |
| Shower Pan | 8/30/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| HVAC-Rough | 9/5/2024 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 9/5/2024 | Approved | WILLIAM SIERRA |
| Sewer | 9/5/2024 | Corrections Issued | WILLIAM SIERRA |
| Shower Pan | 9/5/2024 | Approved | WILLIAM SIERRA |
| Sewer | 9/10/2024 | Approved | WILLIAM SIERRA |
| Drywall Nailing | 9/12/2024 | Conditional Approval | JOHN QUINTANILLA |
| Green Building Rough | 9/12/2024 | Conditional Approval | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 1/22/2025 | Approved | WILLIAM SIERRA |
| Drywall Nailing | 1/22/2025 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Final | 1/22/2025 | Corrections Issued | WILLIAM SIERRA |
| Final | 1/22/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 1/22/2025 | Approved | WILLIAM SIERRA |
| Green Building Rough | 1/22/2025 | Approved | WILLIAM SIERRA |
| HVAC-Final | 1/22/2025 | Approved | WILLIAM SIERRA |
| METHANE-Final | 1/22/2025 | Approved | WILLIAM SIERRA |
| METHANE-Rough | 1/22/2025 | Approved | WILLIAM SIERRA |
| PLUMBING-Final | 1/22/2025 | Approved | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 1/22/2025 | SGSOV No Gas | WILLIAM SIERRA |
| Smoke Detectors | 1/22/2025 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Final | 3/10/2025 | Approved | WILLIAM SIERRA |
| Final | 3/10/2025 | OK to Issue CofO | WILLIAM SIERRA |