5437 N SIMPSON AVE 91607

Certificate Information: 5437 N SIMPSON AVE 91607

Application / Permit
23016-20000-25704
Plan Check / Job No.
B23VN10310
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN. CONVERT (E) DETACHED GARAGE TO (N) DETACHED ADU PER STATE LAW
Permit Issued
Issued on 10/19/2023
Issuing Office
Current Status
CofO Issued on 6/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/2/2023 APPLICANT
Assigned to Plan Check Engineer 8/9/2023 WEIJIAN HUANG
Corrections Issued 8/10/2023 WEIJIAN HUANG
Applicant returned to address corrections 9/15/2023 KHUONG TRUONG
Plan Check Approved 9/27/2023 FERNANDO FLORES
Issued 10/19/2023 APPLICANT
CofO in Progress 5/15/2024 CHRISTOPHER ROJAS
Permit Finaled 6/5/2024 RUBEN SALAS
CofO Issued 6/5/2024 RUBEN SALAS
Permit Finaled 6/5/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/29/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/29/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 8/29/2023 DAGOVERTO GUERRERO
Specific Plan Cleared 8/30/2023 CHRISTIAN PEARSON
Miscellaneous Cleared 9/25/2023 RUBEN VASQUEZ

Contact Information

Contractor G & M Home Remodeling Inc; Lic. No.: 1048107-B       ,
Engineer Chaaya,, Danny Camille; Lic. No.: NA45555       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/20/2023 Approved RYAN SALAZAR
PLUMBING-Rough 11/20/2023 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 12/7/2023 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Final 12/7/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 12/7/2023 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 12/7/2023 Partial Approval KIRK SANDERS
Green Building Rough 12/7/2023 Approved KIRK SANDERS
HVAC-Rough 12/7/2023 Corrections Issued KIRK SANDERS
MERV13>=Rough 12/7/2023 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 12/7/2023 Approved KIRK SANDERS
Underground Mechanical 12/7/2023 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 12/14/2023 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 12/14/2023 Corrections Issued KIRK SANDERS
HVAC-Rough 12/14/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 12/14/2023 Partial Approval KIRK SANDERS
MERV13>=Rough 12/14/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 12/22/2023 Approved KIRK SANDERS
Insulation 12/22/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 1/2/2024 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/2/2024 Approved KIRK SANDERS
Drywall Nailing 1/18/2024 Approved KIRK SANDERS
Interior/Exterior Lathing 1/18/2024 Approved KIRK SANDERS
Shower Pan 1/18/2024 Approved KIRK SANDERS
Final 4/26/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 4/26/2024 Approved CHRISTOPHER ROJAS
MERV13>=Final 4/26/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 4/26/2024 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 4/26/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Final 5/14/2024 OK to Issue CofO CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 5/14/2024 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 5/14/2024 Approved CHRISTOPHER ROJAS