6519-6521 N RIVERTON AVE 91606
Certificate Information: 6519-6521 N RIVERTON AVE 91606
- Application / Permit
- 23016-20000-25461
- Plan Check / Job No.
- B23VN10228
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) GARAGE AND PORTION OF SFD TO (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22.
- Permit Issued
- Issued on 11/2/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 8/5/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 8/10/2023 | APPLICANT |
| Plan Check Approved | 11/2/2023 | ALEC MOUSAKHANIAN |
| Issued | 11/2/2023 | APPLICANT |
| CofO in Progress | 4/9/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 5/1/2024 | RUBEN SALAS |
| CofO Issued | 5/1/2024 | RUBEN SALAS |
| Permit Finaled | 5/1/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/17/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 8/17/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2023 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/2/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 2/9/2024 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 2/23/2024 | Corrections Issued | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 2/23/2024 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 2/26/2024 | Approved | JOHN HAYES |
| Green Building Rough | 2/26/2024 | Approved | JOHN HAYES |
| Insulation | 2/26/2024 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 2/26/2024 | Approved | JOHN HAYES |
| Drywall Nailing | 3/4/2024 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 4/2/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 4/2/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Final | 4/2/2024 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 4/2/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/2/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 4/2/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 4/2/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/8/2024 | Approved | JENNIFER RABUCHIN |
| Final | 4/8/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 4/8/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 4/8/2024 | Approved | JENNIFER RABUCHIN |