1509 N AMALFI DR 90272

Certificate Information: 1509 N AMALFI DR 90272

Application / Permit
23016-20000-25088
Plan Check / Job No.
B23VN10101
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 12/4/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2023 APPLICANT
Assigned to Plan Check Engineer 8/3/2023 JESSE ARELLANO
Corrections Issued 8/4/2023 JESSE ARELLANO
Building Plans Picked Up 8/30/2023 APPLICANT
Applicant returned to address corrections 11/7/2023 RAMA DABADGE
Applicant returned to address corrections 12/1/2023 GIOVANNY CHAVEZ
Issued 12/4/2023 APPLICANT
CofO in Progress 9/19/2024 EVAN COOPER
Permit Finaled 9/26/2024 RICHARD STEINBACH
CofO Issued 9/26/2024 RICHARD STEINBACH
Permit Finaled 9/26/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/30/2023 KIMBERLY HERNANDEZ
Sewer availability Cleared 8/30/2023 KIMBERLY HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 9/6/2023 KIMBERLY HERNANDEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 3/4/2024 Corrections Issued KENNETH NAGLE
Deputy Drilled-In Anchors 3/27/2024 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 4/30/2024 Corrections Issued KEVIN SARGSYAN
Deputy Drilled-In Anchors 5/2/2024 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 5/2/2024 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/24/2024 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/29/2024 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 5/31/2024 Approved EVAN COOPER
PLUMBING-Rough 5/31/2024 Approved EVAN COOPER
BUILDING-Rough-Frame 6/4/2024 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 6/4/2024 Approved KEVIN SARGSYAN
Insulation 6/4/2024 Partial Approval KEVIN SARGSYAN
Interior/Exterior Lathing 6/4/2024 Partial Approval KEVIN SARGSYAN
Interior/Exterior Lathing 6/13/2024 Not Ready for Inspection KEVIN SARGSYAN
Drywall Nailing 6/26/2024 Partial Approval KEVIN SARGSYAN
Interior/Exterior Lathing 6/28/2024 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 7/9/2024 Approved KEVIN SARGSYAN
Insulation 7/11/2024 Approved KEVIN SARGSYAN
Drywall Nailing 7/15/2024 Approved KENNETH NAGLE
Shower Pan 7/18/2024 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 7/19/2024 Approved KEVIN SARGSYAN
HVAC-Final 9/9/2024 Approved KEVIN SARGSYAN
PLUMBING-Final 9/9/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Final 9/10/2024 Approved KEVIN SARGSYAN
Final 9/10/2024 Corrections Issued KEVIN SARGSYAN
Green Building Final 9/10/2024 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 9/10/2024 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 9/10/2024 Approved KEVIN SARGSYAN
Final 9/13/2024 Not Ready for Inspection KEVIN SARGSYAN
Final 9/19/2024 OK to Issue CofO EVAN COOPER