5528 N DENNY AVE 91601
Certificate Information: 5528 N DENNY AVE 91601
- Application / Permit
- 23016-20000-24999
- Plan Check / Job No.
- B23VN10060
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EX. ATTACHED GARAGE TO BEDROOM, ADDITION OF NEW 3'-6"x 6'-3" LAUNDRY CLOSET AND CONVERT EX. FAMILY ROOM TO RECREATION ROOM. "COMPLY WITH DEPARTMENT ORDER effective date 05/17/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 1/10/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2023 | KAMYAR EMAMI |
| Corrections Issued | 8/1/2023 | KAMYAR EMAMI |
| Building Plans Picked Up | 8/4/2023 | APPLICANT |
| Applicant returned to address corrections | 9/21/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 11/6/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 12/4/2023 | OMAR GARNICA |
| Plan Check Approved | 1/10/2024 | ROSENDO MEDINA |
| Issued | 1/10/2024 | APPLICANT |
| CofO in Progress | 3/4/2025 | SCOTT SHUSTER |
| CofO Issued | 6/6/2025 | DAVID JAMES |
| Permit Finaled | 6/6/2025 | DAVID JAMES |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/20/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 11/20/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/18/2024 | Partial Inspection | SCOTT SHUSTER |
| Pre-Inspection | 8/15/2024 | Approved | THOMAS WOODS |
| Deputy Drilled-In Anchors | 10/24/2024 | Approved | THOMAS WOODS |
| Deputy Drilled-In Anchors | 11/22/2024 | Conditional Approval | SCOTT SHUSTER |
| Deputy Wood Construction | 12/3/2024 | Conditional Approval | SCOTT SHUSTER |
| Special/Order Compliance | 12/17/2024 | Partial Approval | SCOTT SHUSTER |
| Interior/Exterior Lathing | 1/16/2025 | Partial Inspection | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 2/7/2025 | Partial Inspection | SCOTT SHUSTER |
| Final | 2/7/2025 | Partial Inspection | SCOTT SHUSTER |
| Footing/Foundation/Slab | 2/7/2025 | Partial Inspection | SCOTT SHUSTER |
| Green Building Final | 2/7/2025 | Partial Inspection | SCOTT SHUSTER |
| Green Building Rough | 2/7/2025 | Approved | SCOTT SHUSTER |
| SGSOV-Seismic Gas S/O Valve | 2/7/2025 | SGSOV Approved | SCOTT SHUSTER |
| Smoke Detectors | 2/7/2025 | Partial Inspection | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 2/20/2025 | Approved | JOSE RUBIO |
| Final | 2/20/2025 | Partial Approval | JOSE RUBIO |
| Footing/Foundation/Slab | 2/20/2025 | Approved | JOSE RUBIO |
| Green Building Final | 2/20/2025 | Approved | JOSE RUBIO |
| METHANE-Barrier | 2/20/2025 | Approved | JOSE RUBIO |
| METHANE-Final | 2/20/2025 | Approved | JOSE RUBIO |
| METHANE-Rough | 2/20/2025 | Approved | JOSE RUBIO |
| METHANE-Subgrade | 2/20/2025 | Approved | JOSE RUBIO |
| Smoke Detectors | 2/20/2025 | Approved | JOSE RUBIO |
| Final | 3/4/2025 | OK to Issue CofO | SCOTT SHUSTER |