13712 W CALVERT ST 91401
Certificate Information: 13712 W CALVERT ST 91401
- Application / Permit
- 23016-20000-24834
- Plan Check / Job No.
- B23VN09964
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL THROUGHOUT (E) SFD. CONVERT PORTION OF SFD TO GARAGE CLOSET. RELOCATE LAUNDRY ROOM, BATHROOM, AND KITCHEN, DEMO FIREPLACE, REMOVE AND REPLACE DOOR AT LIVING ROOM. REMODEL MASTER BATHROOM, MASTER CLOSET, MASTER BEDROOM ENTRY DOOR AND NEW LAUNDRY ROOM ON 2ND FLOOR
- Permit Issued
- Issued on 10/15/2024
- Issuing Office
- Current Status
- CofO Issued on 9/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 8/1/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 9/13/2023 | APPLICANT |
| Plan Check Approved | 11/15/2023 | RAMA DABADGE |
| Issued | 10/15/2024 | APPLICANT |
| CofO in Progress | 9/11/2025 | RYAN SALAZAR |
| CofO Issued | 9/23/2025 | RUBEN SALAS |
| Permit Finaled | 9/23/2025 | RUBEN SALAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Design For Success Inc; Lic. No.: 1051070-B | 21208 COSTANSO STREET #1 WOODLAND HILLS, CA 91364 |
| Engineer | Li,, Dacheng D; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/21/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 11/21/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 1/21/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| HVAC-Rough | 1/21/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 1/24/2025 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Rough | 1/24/2025 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 2/28/2025 | Corrections Issued | RYAN SALAZAR |
| ELECTRICAL-Rough | 2/28/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 2/28/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 2/28/2025 | Approved | RYAN SALAZAR |
| Insulation | 3/7/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 3/7/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/12/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/17/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 3/24/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Non Compliance | 3/24/2025 | Not Required | RYAN SALAZAR |
| Order to Comply | 3/24/2025 | Not Required | RYAN SALAZAR |
| Drywall Nailing | 3/26/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/10/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 9/10/2025 | Approved | RYAN SALAZAR |
| Final | 9/10/2025 | OK to Issue CofO | RYAN SALAZAR |
| HVAC-Final | 9/10/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 9/10/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 9/10/2025 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 9/10/2025 | Approved | RYAN SALAZAR |