8839-8841 N SPARTON AVE 91331

Certificate Information: 8839-8841 N SPARTON AVE 91331

Application / Permit
23016-20000-24656
Plan Check / Job No.
B23VN09911
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Convert (E) garage to a 329 sq.ft. ADU. PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 9/12/2023
Issuing Office
Current Status
CofO Issued on 10/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2023 APPLICANT
Assigned to Plan Check Engineer 8/4/2023 ALFREDO JARA
Corrections Issued 8/6/2023 ALFREDO JARA
Plan Check Approved 8/22/2023 ALFREDO JARA
No Progress 9/12/2023 ALFREDO JARA
Plan Check Approved 9/12/2023 ALFREDO JARA
Issued 9/12/2023 APPLICANT
CofO in Progress 10/9/2024 GREGG CUMMINGS
Permit Finaled 10/21/2024 DANIEL ORRANTE
CofO Issued 10/21/2024 DANIEL ORRANTE
Permit Finaled 10/21/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/14/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 8/14/2023 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 8/14/2023 MEGAN GODINEZ
Sewer availability Cleared 8/14/2023 MEGAN GODINEZ

Contact Information

Architect Sheldon,, Geoffrey; Lic. No.: NA33374       ,
Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Almalla,, Dean; Lic. No.: NA58024       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/3/2024 Partial Approval GREGG CUMMINGS
Sewer 4/3/2024 Approved GREGG CUMMINGS
Deputy Drilled-In Anchors 4/22/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 4/24/2024 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 4/29/2024 Approved KEVIN BERBERYAN
Pre-Inspection 5/8/2024 Corrections Issued GREGG CUMMINGS
BUILDING-Rough-Frame 5/23/2024 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 6/10/2024 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 7/3/2024 Corrections Issued GREGG CUMMINGS
HVAC-Rough 7/3/2024 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 7/3/2024 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 7/8/2024 Approved GREGG CUMMINGS
HVAC-Rough 7/8/2024 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 7/9/2024 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 7/9/2024 Approved GREGG CUMMINGS
PLUMBING-Rough 7/9/2024 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 7/11/2024 Approved GREGG CUMMINGS
Green Building Rough 7/11/2024 Approved GREGG CUMMINGS
PLUMBING-Rough 7/11/2024 Approved GREGG CUMMINGS
Insulation 7/12/2024 Approved GREGG CUMMINGS
Drywall Nailing 7/18/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 7/23/2024 Approved GREGG CUMMINGS
ELECTRICAL-Final 9/12/2024 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Final 9/24/2024 Corrections Issued VINCENT HANLEY
Final 9/24/2024 Corrections Issued VINCENT HANLEY
HVAC-Final 9/24/2024 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/24/2024 SGSOV Approved VINCENT HANLEY
Smoke Detectors 9/24/2024 Approved VINCENT HANLEY
Final 9/27/2024 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Final 10/4/2024 Approved GREGG CUMMINGS
Final 10/4/2024 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 10/4/2024 Approved GREGG CUMMINGS
PLUMBING-Final 10/4/2024 Approved GREGG CUMMINGS