18136 W CHASE ST 91325

Certificate Information: 18136 W CHASE ST 91325

Application / Permit
23016-20000-24641
Plan Check / Job No.
B23VN09902
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT (E) DETACHED GARAGE INTO ADU PER GCS65852.2(e)(1)(A. WORK PER WFPP.
Permit Issued
Issued on 8/12/2023
Issuing Office
Current Status
CofO Issued on 4/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/25/2023 APPLICANT
Assigned to Plan Check Engineer 8/2/2023 ISIS ARGUETA
Corrections Issued 8/2/2023 ISIS ARGUETA
Plan Check Approved 8/9/2023 ISIS ARGUETA
Issued 8/12/2023 APPLICANT
CofO in Progress 4/2/2024 KRISTEN BEVERIDGE
Permit Finaled 4/5/2024 JOHN JANSON
CofO Issued 4/5/2024 JOHN JANSON
Permit Finaled 4/5/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/4/2023 CARLOS AGUILERA
Sewer availability Cleared 8/4/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/7/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/30/2023 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 10/31/2023 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 11/8/2023 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 11/8/2023 Approved JOHN KIDWELL
PLUMBING-Rough 11/8/2023 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 11/16/2023 Approved JOHN KIDWELL
BUILDING-Rough-Frame 11/29/2023 Corrections Issued DAVID SCANTLIN
Gas Test 11/29/2023 Approved DAVID SCANTLIN
Insulation 11/29/2023 Corrections Issued DAVID SCANTLIN
BUILDING-Rough-Frame 12/13/2023 Approved DAVID SCANTLIN
Insulation 12/13/2023 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 12/13/2023 Approved DAVID SCANTLIN
Final 12/15/2023 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 12/15/2023 SGSOV Not Ready DAVID SCANTLIN
Smoke Detectors 12/15/2023 No Access for Inspection DAVID SCANTLIN
Drywall Nailing 12/18/2023 Approved DAVID SCANTLIN
Interior/Exterior Lathing 1/23/2024 Approved DAVID SCANTLIN
Final 3/7/2024 Corrections Issued DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 3/7/2024 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 3/7/2024 Approved DAVID SCANTLIN
Final 3/26/2024 Not Ready for Inspection KRISTEN CAUSEY
Final 4/1/2024 OK to Issue CofO KRISTEN CAUSEY