7142-7144 N GATESHEAD WAY 91307

Certificate Information: 7142-7144 N GATESHEAD WAY 91307

Application / Permit
23016-20000-24422
Plan Check / Job No.
B23VN09804
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING GARAGE TO NEW ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A)
Permit Issued
Issued on 8/8/2023
Issuing Office
Current Status
CofO Issued on 3/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2023 APPLICANT
Assigned to Plan Check Engineer 7/28/2023 SERGIO MUNIZ
Corrections Issued 8/1/2023 SERGIO MUNIZ
Building Plans Picked Up 8/2/2023 APPLICANT
Plan Check Approved 8/8/2023 ALEC MOUSAKHANIAN
Issued 8/8/2023 APPLICANT
CofO in Progress 3/8/2024 JEFFREY HARTLINE
Permit Finaled 3/18/2024 JOHN JANSON
CofO Issued 3/18/2024 JOHN JANSON
Permit Finaled 3/18/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/3/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/3/2023 CARLOS AGUILERA
Sewer availability Cleared 8/3/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Foroughikia,, Babak; Lic. No.: C94091 21930 MARYLEE ST APT 87      WOODLAND HILLS, CA 91367

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/31/2023 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 9/5/2023 Partial Approval DAVID SCANTLIN
Deputy Drilled-In Anchors 9/7/2023 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 9/8/2023 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 10/2/2023 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 10/2/2023 Corrections Issued JEFFREY HARTLINE
PLUMBING-Rough 10/2/2023 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 10/5/2023 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 10/5/2023 Not Ready for Inspection JEFFREY HARTLINE
Pre-Inspection 10/5/2023 Approved JEFFREY HARTLINE
Shower Pan 10/5/2023 Corrections Issued JEFFREY HARTLINE
Insulation 10/10/2023 Approved JEFFREY HARTLINE
Drywall Nailing 10/16/2023 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 10/16/2023 Approved JEFFREY HARTLINE
Shower Pan 10/16/2023 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 1/4/2024 No Access for Inspection JEFFREY HARTLINE
Final 1/4/2024 No Access for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 1/4/2024 SGSOV Not Ready JEFFREY HARTLINE
Smoke Detectors 1/4/2024 No Access for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 1/30/2024 Approved JEFFREY HARTLINE
Final 1/30/2024 Corrections Issued JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 1/30/2024 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 1/30/2024 Approved JEFFREY HARTLINE
Final 3/7/2024 OK to Issue CofO JEFFREY HARTLINE