7418-7420 N VANALDEN AVE 91335

Certificate Information: 7418-7420 N VANALDEN AVE 91335

Application / Permit
23016-20000-24080
Plan Check / Job No.
B23VN09669
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 8/25/2023
Issuing Office
Valley
Current Status
CofO Issued on 2/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/20/2023 APPLICANT
Assigned to Plan Check Engineer 7/26/2023 JESSE ARELLANO
Corrections Issued 7/27/2023 JESSE ARELLANO
Building Plans Picked Up 8/9/2023 APPLICANT
Plan Check Approved 8/25/2023 ISIS ARGUETA
Issued 8/25/2023 APPLICANT
CofO in Progress 2/2/2024 JEFFREY HARTLINE
Permit Finaled 2/20/2024 JOHN JANSON
CofO Issued 2/20/2024 JOHN JANSON
Permit Finaled 2/20/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/15/2023 MEGAN GODINEZ
Sewer availability Cleared 8/15/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 8/23/2023 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/11/2023 Approved DAVID SCANTLIN
PLUMBING-Rough 9/25/2023 Approved JEFFREY BULL
Sewer 9/25/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 10/2/2023 Approved JEFFREY BULL
ELECTRICAL-Rough 10/2/2023 Approved JEFFREY BULL
Gas Test 10/2/2023 Approved JEFFREY BULL
Green Building Rough 10/2/2023 Approved JEFFREY BULL
PLUMBING-Rough 10/2/2023 Approved JEFFREY BULL
Insulation 10/12/2023 Corrections Issued JEFFREY BULL
Drywall Nailing 10/25/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 10/25/2023 Partial Approval JEFFREY BULL
Shower Pan 10/25/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 10/31/2023 Approved JEFFREY BULL
ELECTRICAL-Final 1/29/2024 Approved JEFFREY BULL
Final 1/29/2024 Corrections Issued JEFFREY BULL
Green Building Final 1/29/2024 Not Ready for Inspection JEFFREY BULL
HVAC-Final 1/29/2024 Not Ready for Inspection JEFFREY BULL
PLUMBING-Final 1/29/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 1/29/2024 SGSOV Approved JEFFREY BULL
Smoke Detectors 1/29/2024 Approved JEFFREY BULL
ELECTRICAL-Final 2/2/2024 Approved JEFFREY HARTLINE
Final 2/2/2024 OK to Issue CofO JEFFREY HARTLINE
Green Building Final 2/2/2024 Approved JEFFREY HARTLINE
HVAC-Final 2/2/2024 Approved JEFFREY HARTLINE
PLUMBING-Final 2/2/2024 Approved JEFFREY HARTLINE