10341 N FERNGLEN AVE 91042

Certificate Information: 10341 N FERNGLEN AVE 91042

Application / Permit
23016-20000-24020
Plan Check / Job No.
B23VN09648
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan-CONVERT EXISTING GARAGE TO ACCESSORY DWELLING UNIT PER STATE LAW.
Permit Issued
Issued on 8/21/2023
Issuing Office
Current Status
CofO Issued on 4/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2023 APPLICANT
Assigned to Plan Check Engineer 7/31/2023 MINA HABILI
Corrections Issued 8/1/2023 MINA HABILI
Applicant returned to address corrections 8/12/2023 MINA HABILI
Plan Check Approved 8/17/2023 WEIJIAN HUANG
Issued 8/21/2023 APPLICANT
CofO in Progress 3/24/2025 WILLIAM WREN
Permit Finaled 4/2/2025 RUBEN SALAS
CofO Issued 4/2/2025 RUBEN SALAS
Permit Finaled 4/2/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/4/2023 MEGAN GODINEZ
Sewer availability Cleared 8/4/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 8/7/2023 MEGAN GODINEZ
Grading Pre-Inspection Cleared 8/9/2023 SERGIO VALENZUELA

Contact Information

Architect , ; Lic. No.: C37632       ,
Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/8/2024 Partial Approval WILLIAM WREN
Footing/Foundation/Slab 5/14/2024 Corrections Issued WILLIAM WREN
Deputy Drilled-In Anchors 5/15/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 5/16/2024 Approved WILLIAM WREN
BUILDING-Rough-Frame 6/10/2024 Approved WILLIAM WREN
ELECTRICAL-Rough 6/10/2024 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Approved WILLIAM WREN
Green Building Rough 6/10/2024 Approved WILLIAM WREN
HVAC-Rough 6/10/2024 Approved WILLIAM WREN
PLUMBING-Rough 6/10/2024 Approved WILLIAM WREN
Interior/Exterior Lathing 7/12/2024 Partial Approval WILLIAM WREN
Insulation 7/18/2024 Approved DAVID ANDERSON
Drywall Nailing 7/22/2024 Approved DAVID ANDERSON
Shower Pan 7/22/2024 Not Ready for Inspection DAVID ANDERSON
Interior/Exterior Lathing 9/5/2024 Approved WILLIAM WREN
Shower Pan 9/5/2024 Approved WILLIAM WREN
ELECTRICAL-Final 2/14/2025 Approved MICHEL ABAJAN
Final 2/14/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 2/14/2025 Approved MICHEL ABAJAN
HVAC-Final 2/14/2025 Approved MICHEL ABAJAN
PLUMBING-Final 2/14/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 2/14/2025 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 2/14/2025 Approved MICHEL ABAJAN
Final 3/10/2025 OK to Issue CofO WILLIAM WREN