1213-1217 1/2 E 51ST ST 90011

Certificate Information: 1213-1217 1/2 E 51ST ST 90011

Application / Permit
23016-20000-23656
Plan Check / Job No.
B23VN09557
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) THREE CAR GARAGE AT FIRST FLOOR OF THE (E) TWO STORY DUPLEX W/ATT. CARPORT AT FIRST FLOOR INTO A NEW ACCESSORY DWELLING UNIT (500 S.F) PER CA Govt. Code 65852.2(e)(1)(C). (ADU IS 1217 1/2 51ST ST)
Permit Issued
Issued on 4/3/2024
Issuing Office
Current Status
CofO Issued on 1/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2023 APPLICANT
Assigned to Plan Check Engineer 8/1/2023 SARKIS HARABEDIAN
Corrections Issued 8/2/2023 SARKIS HARABEDIAN
Plan Check Approved 1/1/2024 OMAR GARNICA
Issued 4/3/2024 APPLICANT
CofO in Progress 1/10/2025 ALEJANDRO DE ARTOLA
Permit Finaled 1/26/2025 DEROLD HAUFF
CofO Issued 1/26/2025 DEROLD HAUFF
Permit Finaled 1/26/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/18/2023 HUGO LOPEZ
Sewer availability Cleared 8/18/2023 HUGO LOPEZ
Construction near power lines Cleared 11/27/2023 RIDWAN HARDY
Construction within easement Cleared 11/27/2023 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 12/19/2023 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/17/2024 Corrections Issued DAVID FEILER
PLUMBING-Rough 6/17/2024 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 6/20/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/20/2024 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 7/16/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 7/16/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/16/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/23/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 7/23/2024 Approved ALEJANDRO DE ARTOLA
Green Building Rough 7/23/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 7/23/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 8/1/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 8/7/2024 Approved ALEX COLIN
Interior/Exterior Lathing 8/7/2024 Approved ALEX COLIN
ELECTRICAL-Final 9/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 9/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 9/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 9/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 9/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 9/24/2024 Approved ALEJANDRO DE ARTOLA
Final 9/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 9/24/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 9/24/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 9/24/2024 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 9/24/2024 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 9/24/2024 Approved ALEJANDRO DE ARTOLA
Final 10/1/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 12/30/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 1/10/2025 OK to Issue CofO ALEJANDRO DE ARTOLA