22151 W COHASSET ST 91303
Certificate Information: 22151 W COHASSET ST 91303
- Application / Permit
- 23016-20000-23616
- Plan Check / Job No.
- B23VN09548
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE INTO A NEW 21'-6" x 20'-0" ACCESSORY DWELLING UNIT PER GC 66323(a)(1).
- Permit Issued
- Issued on 12/26/2025
- Issuing Office
- Valley
- Current Status
- Issued on 12/26/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2023 | JESSE ARELLANO |
| Corrections Issued | 7/25/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 7/31/2023 | APPLICANT |
| Applicant returned to address corrections | 9/1/2023 | SARKIS HARABEDIAN |
| Plan Check Approved | 8/6/2025 | OMAR GARNICA |
| Issued | 12/26/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/31/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 7/31/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2023 | TAL SHEMEN |
| Construction near power lines | Cleared | 11/18/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/18/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dianati,, Roxana; Lic. No.: C85100 | 22514 BLUERIDGE COURT CALABASAS, CA 91302 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Service/Power Release | 7/21/2026 |
| Green Building Final | 7/21/2026 |
| Final | 7/21/2026 |
Inspection Request History
| Deputy Drilled-In Anchors | 1/5/2026 | Conditional Approval | JEFFREY HARTLINE |
| Sewer | 1/7/2026 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 1/8/2026 | Approved | KRISTEN CAUSEY |
| PLUMBING-Rough | 1/8/2026 | Partial Approval | KRISTEN CAUSEY |
| Sewer | 1/8/2026 | Approved | KRISTEN CAUSEY |
| Underground Mechanical | 1/14/2026 | Approved | JEFFREY HARTLINE |
| Gas Test | 2/10/2026 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 2/10/2026 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 3/23/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 3/23/2026 | Approved | DAVID SCANTLIN |
| Green Building Rough | 3/23/2026 | Approved | DAVID SCANTLIN |
| Deputy Wood Construction | 3/24/2026 | Conditional Approval | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 3/27/2026 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 3/27/2026 | Partial Approval | JEFFREY HARTLINE |
| Shower Pan | 3/27/2026 | Approved | JEFFREY HARTLINE |
| Wood Frame | 3/27/2026 | Approved | JEFFREY HARTLINE |
| Insulation | 4/6/2026 | Corrections Issued | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 4/6/2026 | Partial Approval | JEFFREY HARTLINE |
| Insulation | 4/14/2026 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 4/22/2026 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 4/22/2026 | SGSOV Approved | JEFFREY HARTLINE |
| Final | 7/15/2026 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 7/15/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| Service/Power Release | 7/15/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| Smoke Detectors | 7/15/2026 | Approved | JEFFREY HARTLINE |