6035 N FALLBROOK AVE 91367
Certificate Information: 6035 N FALLBROOK AVE 91367
- Application / Permit
- 23016-20000-23583
- Plan Check / Job No.
- B23VN09532
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT UNPERMITED 1-STORY DETACHED, MANUFACTURED HOME TO ADU, (21'-7"x59'-0"), 1200 SQFT PER 65852.2(d)(2)
- Permit Issued
- Issued on 10/20/2023
- Issuing Office
- Current Status
- CofO Issued on 5/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2023 | PETER MOSESIAN |
| Corrections Issued | 7/23/2023 | PETER MOSESIAN |
| Quality Review Completed | 7/27/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 8/1/2023 | APPLICANT |
| Plan Check Approved | 10/20/2023 | PETER MOSESIAN |
| Issued | 10/20/2023 | APPLICANT |
| CofO in Progress | 2/29/2024 | TROY SANDERS |
| Permit Finaled | 5/24/2024 | JOHN JANSON |
| CofO Issued | 5/24/2024 | JOHN JANSON |
| Permit Finaled | 5/24/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/26/2023 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 8/26/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 8/28/2023 | COLIN LOREDO |
| ZA Case | Cleared | 9/1/2023 | STEVEN WECHSLER |
| ZA Case | Cleared | 9/1/2023 | STEVEN WECHSLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 28025 DOROTHY DR STE 202 AGOURA HILLS, CA 91301 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/30/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 12/13/2023 | No Access for Inspection | MORRIS JACKSON |
| Drywall Nailing | 12/13/2023 | No Access for Inspection | MORRIS JACKSON |
| Final | 12/13/2023 | No Access for Inspection | MORRIS JACKSON |
| Green Building Final | 12/13/2023 | No Access for Inspection | MORRIS JACKSON |
| Green Building Rough | 12/13/2023 | No Access for Inspection | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Not Ready | MORRIS JACKSON |
| Smoke Detectors | 12/13/2023 | No Access for Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 12/19/2023 | Approved | TROY SANDERS |
| Drywall Nailing | 12/19/2023 | Approved | TROY SANDERS |
| Final | 12/19/2023 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 12/19/2023 | Not Ready for Inspection | TROY SANDERS |
| Green Building Rough | 12/19/2023 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 12/19/2023 | Approved | TROY SANDERS |
| Final | 2/29/2024 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 2/29/2024 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 5/24/2024 | Approved | TROY SANDERS |