7155-7157 N ROYER AVE 91307

Certificate Information: 7155-7157 N ROYER AVE 91307

Application / Permit
23016-20000-23582
Plan Check / Job No.
B23VN09528
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATT. GARAGE TO LAUNDRY ROOM AND ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 10/18/2023
Issuing Office
Current Status
CofO Issued on 10/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2023 APPLICANT
Assigned to Plan Check Engineer 7/24/2023 JESSE ARELLANO
Corrections Issued 7/25/2023 JESSE ARELLANO
Building Plans Picked Up 7/31/2023 APPLICANT
Plan Check Approved 8/17/2023 ANGELICA MARTINEZ
Issued 10/18/2023 APPLICANT
CofO in Progress 10/23/2024 CHRIS CHRISTENSEN
Permit Finaled 10/24/2024 JOHN JANSON
CofO Issued 10/24/2024 JOHN JANSON
Permit Finaled 10/24/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/2/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 8/2/2023 ROMAN GUTIERREZ
Sewer availability Cleared 8/2/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/4/2024 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 3/5/2024 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 3/7/2024 Partial Approval KRISTEN CAUSEY
Sewer 3/7/2024 Not Ready for Inspection KRISTEN CAUSEY
PLUMBING-Rough 5/20/2024 Approved CHRIS CHRISTENSEN
Sewer 5/20/2024 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 7/5/2024 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 7/5/2024 Partial Approval JEFFREY HARTLINE
BUILDING-Rough-Frame 7/17/2024 Approved CHRIS CHRISTENSEN
Green Building Rough 7/17/2024 Approved CHRIS CHRISTENSEN
HVAC-Rough 7/17/2024 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 7/17/2024 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 7/23/2024 Approved CHRIS CHRISTENSEN
Insulation 7/23/2024 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Partial Approval TROY SANDERS
Insulation 7/30/2024 Partial Approval TROY SANDERS
Wood Frame 7/30/2024 Not Ready for Inspection TROY SANDERS
Insulation 8/16/2024 Approved CHRIS CHRISTENSEN
Wood Frame 8/16/2024 Approved CHRIS CHRISTENSEN
Drywall Nailing 8/21/2024 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/28/2024 Approved CHRIS CHRISTENSEN
Shower Pan 8/28/2024 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 9/30/2024 Approved CHRIS CHRISTENSEN
Final 9/30/2024 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 9/30/2024 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Final 9/30/2024 Approved CHRIS CHRISTENSEN
PLUMBING-Final 9/30/2024 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 9/30/2024 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 9/30/2024 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 10/21/2024 Approved CHRIS CHRISTENSEN
Final 10/21/2024 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 10/21/2024 Approved CHRIS CHRISTENSEN
HVAC-Final 10/21/2024 Approved CHRIS CHRISTENSEN
PLUMBING-Final 10/21/2024 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/21/2024 SGSOV Approved CHRIS CHRISTENSEN