10834 W WICKS ST 91040

Certificate Information: 10834 W WICKS ST 91040

Application / Permit
23016-20000-23344
Plan Check / Job No.
B23VN09453
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT (E) DETACHED GARAGE TO ADU PER GCS 65852.2(e)(1)(A). WORK PER WFPP.
Permit Issued
Issued on 8/23/2023
Issuing Office
Current Status
CofO Issued on 7/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2023 APPLICANT
Assigned to Plan Check Engineer 7/26/2023 ISIS ARGUETA
Corrections Issued 7/27/2023 ISIS ARGUETA
Plan Check Approved 8/16/2023 ISIS ARGUETA
Issued 8/23/2023 APPLICANT
CofO in Progress 4/14/2024 DAVID ANDERSON
CofO in Progress 4/24/2025 DAVID ANDERSON
CofO in Progress 6/2/2025 DAVID ANDERSON
Permit Finaled 7/10/2025 RUBEN SALAS
CofO Issued 7/10/2025 RUBEN SALAS
Permit Finaled 7/10/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/28/2023 LEE GUILBEAUX
Sewer availability Cleared 7/28/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/1/2023 LEE GUILBEAUX
ZA Case Cleared 8/1/2023 STEVEN WECHSLER
Grading Pre-Inspection Cleared 8/16/2023 ISIS ARGUETA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/27/2023 Partial Approval DAVID ANDERSON
Footing/Foundation/Slab 11/15/2023 Approved DAVID ANDERSON
ELECTRICAL-Rough 12/11/2023 Not Ready for Inspection DAVID ANDERSON
HVAC-Rough 12/11/2023 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 12/11/2023 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 12/14/2023 Approved DAVID ANDERSON
HVAC-Rough 12/14/2023 Approved DAVID ANDERSON
PLUMBING-Rough 12/14/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 12/19/2023 Partial Approval WILLIAM WREN
Wood Frame 12/19/2023 Approved WILLIAM WREN
Insulation 12/21/2023 Approved DAVID ANDERSON
Drywall Nailing 12/26/2023 Approved DAVID ANDERSON
Shower Pan 12/26/2023 Corrections Issued DAVID ANDERSON
Interior/Exterior Lathing 12/29/2023 Approved DAVID ANDERSON
Shower Pan 12/29/2023 Approved DAVID ANDERSON
ELECTRICAL-Final 4/10/2024 Corrections Issued DAVID ANDERSON
HVAC-Final 4/10/2024 Corrections Issued DAVID ANDERSON
PLUMBING-Final 4/10/2024 Approved DAVID ANDERSON
BUILDING-Rough-Frame 4/12/2024 Approved DAVID ANDERSON
Final 4/12/2024 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 4/12/2024 SGSOV Approved DAVID ANDERSON
Smoke Detectors 4/12/2024 Approved DAVID ANDERSON
Final 4/24/2025 Corrections Issued DAVID ANDERSON
Final 5/30/2025 OK to Issue CofO DAVID ANDERSON