6803 W FOOTHILL BLVD 91042
Certificate Information: 6803 W FOOTHILL BLVD 91042
- Application / Permit
- 23016-20000-23299
- Plan Check / Job No.
- B23VN09425
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Dental Clinic
- Work Description
- CHANGE OF USE FROM (E) DWELLING UNIT AND OFFICE TO NEW DENTAL CLINIC AND T.I. (863 SF)
- Permit Issued
- Issued on 12/3/2024
- Issuing Office
- Current Status
- CofO Issued on 6/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2023 | SEAN SHAHMIRI |
| Corrections Issued | 7/24/2023 | SEAN SHAHMIRI |
| Quality Review Completed | 7/28/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 1/5/2024 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 1/12/2024 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 2/5/2024 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 11/14/2024 | SEAN SHAHMIRI |
| Plan Check Approved | 12/2/2024 | SEAN SHAHMIRI |
| Issued | 12/3/2024 | APPLICANT |
| CofO in Progress | 6/4/2025 | ANDREW DORSO |
| Permit Finaled | 6/9/2025 | RICKEY JACKSON |
| CofO Issued | 6/9/2025 | RICKEY JACKSON |
| Permit Finaled | 6/9/2025 | RICKEY JACKSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/1/2023 | LEE GUILBEAUX |
| Specific Plan | Cleared | 10/18/2023 | ERICK MARCHENA |
| Comm Cor/Mini-Mall | Cleared | 10/31/2023 | ALEX VELA |
| DAS Clearance | Cleared | 2/14/2024 | Rosendo Medina |
| SB8 RUD | Cleared | 10/23/2024 | SAMANTHA RIVERA |
| ZI | Cleared | 11/5/2024 | NATHAN ROMINE |
Contact Information
| Contractor | Garrett Construction Inc; Lic. No.: 974349-B | , |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/9/2024 | Conditional Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 12/9/2024 | Partial Approval | ANDREW DORSO |
| Wood Frame | 12/13/2024 | Not Ready for Inspection | ANDREW DORSO |
| Insulation | 12/19/2024 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 12/19/2024 | Not Ready for Inspection | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2024 | Partial Approval | JOHN KITCKO |
| Special/Order Compliance | 12/20/2024 | Partial Approval | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2024 | Approved | ANDREW DORSO |
| Interior/Exterior Lathing | 1/3/2025 | Approved | ANDREW DORSO |
| Light Gage Steel Frame | 1/15/2025 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 1/16/2025 | Not Ready for Inspection | ANDREW DORSO |
| Insulation | 1/17/2025 | Approved | ANDREW DORSO |
| Drywall Nailing | 1/23/2025 | Approved | ANDREW DORSO |
| Final | 5/13/2025 | Not Ready for Inspection | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 5/13/2025 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 5/13/2025 | Approved | ANDREW DORSO |
| Final | 6/4/2025 | OK to Issue CofO | ANDREW DORSO |