7743 N PASO ROBLES AVE 91406
Certificate Information: 7743 N PASO ROBLES AVE 91406
- Application / Permit
- 23016-20000-23058
- Plan Check / Job No.
- B23VN09342
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL TO EX. SFD. ENLARGE MASTER BATHROOM. REMODEL KITCHEN AREA AND EX. BATHROOMS. RELOCATE ENTRY DOOR. REPLACE WINDOW WITH SLIDING DOOR. WORK PER ENGINEER.
- Permit Issued
- Issued on 7/13/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 12/27/2023
Permit Application Status History
| Submitted | 7/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2023 | ROSENDO MEDINA |
| Plan Check Approved | 7/13/2023 | ROSENDO MEDINA |
| Issued | 7/13/2023 | APPLICANT |
| Permit Finaled | 12/27/2023 | RAUL OLAGI |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 19145 MALABAR ST SANTA CLARITA, CA 91351 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/20/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/20/2023 | Partial Approval | JUAN VALENZUELA |
| Wood Frame | 7/20/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/4/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 8/4/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 8/4/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 8/4/2023 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Rough | 8/10/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 8/10/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 8/17/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 8/17/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 8/17/2023 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 8/17/2023 | Approved | RAUL OLAGI |
| Insulation | 8/23/2023 | Approved | RAUL OLAGI |
| Shower Pan | 8/23/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 8/25/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 8/30/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 12/20/2023 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 12/20/2023 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 12/20/2023 | Approved | MATTHEW NELSON |
| Final | 12/27/2023 | Permit Finaled | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 12/27/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 12/27/2023 | Approved | RAUL OLAGI |