7741 N PASO ROBLES AVE 91406
Certificate Information: 7741 N PASO ROBLES AVE 91406
- Application / Permit
- 23016-20000-23055
- Plan Check / Job No.
- B23VN09340
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 8/24/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2023 | SERGIO MUNIZ |
| Corrections Issued | 7/20/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 7/24/2023 | APPLICANT |
| Issued | 8/24/2023 | APPLICANT |
| CofO in Progress | 3/1/2024 | RAUL OLAGI |
| Permit Finaled | 4/2/2024 | RUBEN SALAS |
| CofO Issued | 4/2/2024 | RUBEN SALAS |
| Permit Finaled | 4/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/26/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/26/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 19145 MALABAR ST SANTA CLARITA, CA 91351 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/28/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 9/25/2023 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 9/25/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 9/25/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 9/25/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 9/29/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 9/29/2023 | Approved | RAUL OLAGI |
| Insulation | 9/29/2023 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 9/29/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 10/4/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 10/4/2023 | Approved | RAUL OLAGI |
| Insulation | 10/4/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 10/4/2023 | Partial Approval | RAUL OLAGI |
| Drywall Nailing | 10/13/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 10/13/2023 | Approved | RAUL OLAGI |
| Shower Pan | 10/13/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 12/20/2023 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 12/20/2023 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 12/20/2023 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 12/27/2023 | Approved | RAUL OLAGI |
| Final | 12/27/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 12/27/2023 | Approved | RAUL OLAGI |
| HVAC-Final | 12/27/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 12/27/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 12/27/2023 | Approved | RAUL OLAGI |
| Final | 2/7/2024 | Corrections Issued | RAUL OLAGI |
| Final | 3/1/2024 | OK to Issue CofO | RAUL OLAGI |