5852-5852 1/2 N COLFAX AVE 91601
Certificate Information: 5852-5852 1/2 N COLFAX AVE 91601
- Application / Permit
- 23016-20000-23015
- Plan Check / Job No.
- B23VN09326
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. Convert existing 4 car garage to two new adu's per CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g). NFPA 13D sprinkler is required thru-out. All work done per engineer.
- Permit Issued
- Issued on 2/21/2024
- Issuing Office
- Current Status
- CofO Issued on 4/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2023 | NAREG ATARIAN |
| Corrections Issued | 9/26/2023 | NAREG ATARIAN |
| Quality Review Completed | 9/28/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 10/23/2023 | NAREG ATARIAN |
| Applicant returned to address corrections | 10/31/2023 | NAREG ATARIAN |
| Plan Check Approved | 10/31/2023 | NAREG ATARIAN |
| No Progress | 10/31/2023 | NAREG ATARIAN |
| Plan Check Approved | 2/8/2024 | NAREG ATARIAN |
| Issued | 2/21/2024 | APPLICANT |
| CofO in Progress | 3/4/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 4/1/2025 | RUBEN SALAS |
| CofO Issued | 4/1/2025 | RUBEN SALAS |
| Permit Finaled | 4/1/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/18/2023 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 10/18/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 10/18/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2023 | NIKKI ZULUETA |
| Green Code | Cleared | 10/26/2023 | MICHAEL AYERS |
| Construction near power lines | Cleared | 2/3/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/3/2024 | RIDWAN HARDY |
Contact Information
| Architect | Feld,, Dovid Yitzchak; Lic. No.: NA37588 | , |
| Architect | Mcvay,, Bruce Cameron; Lic. No.: C11870 | 6440 E. EL ROBLE STREET LONG BEACH, CA 90815 |
| Contractor | J T M Corp; Lic. No.: 1097374-B | , |
| Contractor | Jtm Corporation; Lic. No.: 1097374-B | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/29/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 5/2/2024 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 5/2/2024 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 7/29/2024 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 7/29/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 7/29/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 7/29/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 8/22/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 8/22/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 8/22/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 8/22/2024 | Approved | CHRISTOPHER ROJAS |
| Wood Frame | 8/22/2024 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 8/27/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 8/27/2024 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 8/27/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 9/3/2024 | Approved | MICHAEL CORTEZ |
| Sewer | 9/16/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 1/6/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 1/6/2025 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 1/6/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/6/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 1/9/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 1/9/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 1/17/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Final | 1/17/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 1/22/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Final | 2/7/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 2/7/2025 | SGSOV Not Required | CHRISTOPHER ROJAS |