21021 W OSBORNE ST 91304
Certificate Information: 21021 W OSBORNE ST 91304
- Application / Permit
- 23016-20000-22936
- Plan Check / Job No.
- B23VN09297
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- ePlan *** PROPOSED TENANT IMPROVEMENT AND INTERIOR ALTERATION TO EXPAND WAREHOUSE SPACE; WORK TO INCLUDE NEW RESTROOMS, BREAKROOM AND ROOFTOP EQUIPMENT
- Permit Issued
- Issued on 5/19/2025
- Issuing Office
- Current Status
- Permit Finaled on 9/24/2025
Permit Application Status History
| Submitted | 7/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2023 | SINA KHOSRAVI |
| Corrections Issued | 7/24/2023 | SINA KHOSRAVI |
| Quality Review Completed | 7/26/2023 | GARO TELMI |
| Applicant returned to address corrections | 9/8/2023 | SINA KHOSRAVI |
| Plan Check Approved | 9/27/2023 | SINA KHOSRAVI |
| Issued | 5/19/2025 | APPLICANT |
| Permit Finaled | 9/4/2025 | DEANDRE HOFFMAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 8/2/2023 | BRENNEN OBETO |
| Sewer availability | Cleared | 8/2/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 8/7/2023 | NIKKI ZULUETA |
| Green Code | Cleared | 8/30/2023 | MICHAEL AYERS |
| DAS Clearance | Cleared | 9/18/2023 | Hernan Arreola |
Contact Information
| Contractor | Esplanade Builders Inc; Lic. No.: 831964-B | , |
| Engineer | Rosepink,, Dustin; Lic. No.: S5885 | 24255 VIA MADRUGADA MISSION VIEJO, CA 92692 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 6/30/2025 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 7/14/2025 | Partial Approval | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 7/14/2025 | Partial Approval | DEANDRE HOFFMAN |
| Green Building Rough | 7/14/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 7/14/2025 | Partial Approval | DEANDRE HOFFMAN |
| Insulation | 7/16/2025 | Partial Approval | BRIAN KELLY |
| Drywall Nailing | 7/18/2025 | Partial Approval | DEANDRE HOFFMAN |
| Insulation | 7/23/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| T-Bar Ceiling | 8/13/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Final | 9/4/2025 | Permit Finaled | DEANDRE HOFFMAN |
| Green Building Final | 9/4/2025 | Approved | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 9/4/2025 | SGSOV Approved | DEANDRE HOFFMAN |
| Smoke Detectors | 9/4/2025 | Approved | DEANDRE HOFFMAN |