7945-7947 N BELLAIRE AVE 91605
Certificate Information: 7945-7947 N BELLAIRE AVE 91605
- Application / Permit
- 23016-20000-22787
- Plan Check / Job No.
- B23VN09233
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PORTION OF SFD TO JUNIOR ACCESSORY DWELLING UNIT (415 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22
- Permit Issued
- Issued on 7/25/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 7/18/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 7/20/2023 | APPLICANT |
| Issued | 7/25/2023 | APPLICANT |
| CofO in Progress | 1/12/2024 | GREGG CUMMINGS |
| Permit Finaled | 1/24/2024 | RUBEN SALAS |
| CofO Issued | 1/24/2024 | RUBEN SALAS |
| Permit Finaled | 1/24/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/19/2023 | CARLOS AGUILERA |
| ZA Case | Cleared | 7/20/2023 | ASHLEY RODARTE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/25/2023 | Partial Approval | GREGG CUMMINGS |
| Rough-Elec/Plmb/HVAC | 9/25/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Drywall Nailing | 9/29/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 9/29/2023 | Approved | GREGG CUMMINGS |
| Gas Test | 9/29/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 9/29/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 9/29/2023 | Partial Approval | GREGG CUMMINGS |
| Special/Order Compliance | 9/29/2023 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/13/2023 | Approved | GREGG CUMMINGS |
| Final | 12/13/2023 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 12/13/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 12/29/2023 | OK to Issue CofO | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 12/29/2023 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 12/29/2023 | Approved | GREGG CUMMINGS |