20127-20129 W HAYNES ST 91306
Certificate Information: 20127-20129 W HAYNES ST 91306
- Application / Permit
- 23016-20000-22786
- Plan Check / Job No.
- B23VN09232
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER WFPP AND ENGINEERING DETAILS.
- Permit Issued
- Issued on 7/28/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 7/20/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 7/21/2023 | APPLICANT |
| Plan Check Approved | 7/28/2023 | GIOVANNY CHAVEZ |
| Issued | 7/28/2023 | APPLICANT |
| CofO in Progress | 3/13/2024 | ALEXANDER HANDY |
| Permit Finaled | 4/9/2024 | JOHN JANSON |
| CofO Issued | 4/9/2024 | JOHN JANSON |
| Permit Finaled | 4/9/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/24/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/24/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2023 | DAGOVERTO GUERRERO |
| ZI | Cleared | 7/25/2023 | ALEX VELA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Xiaoran; Lic. No.: C78408 | 1675 COLBY AVE APT 4 WEST LOS ANGELES, CA 90025 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/30/2023 | Conditional Approval | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 9/5/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 9/5/2023 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 10/18/2023 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 10/18/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 10/18/2023 | Approved | ALEXANDER HANDY |
| Sewer | 10/18/2023 | Approved | ALEXANDER HANDY |
| Insulation | 10/31/2023 | Approved | ALEXANDER HANDY |
| Wood Frame | 10/31/2023 | Partial Approval | ALEXANDER HANDY |
| Drywall Nailing | 11/9/2023 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 12/8/2023 | Approved | ALEXANDER HANDY |
| Shower Pan | 12/8/2023 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 2/2/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| FLOOD-Proofing Certificate | 2/2/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| Final | 2/2/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| Green Building Final | 2/2/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| Green Building Rough | 2/2/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| SGSOV-Seismic Gas S/O Valve | 2/2/2024 | SGSOV Not Ready | KRISTEN CAUSEY |
| Smoke Detectors | 2/2/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 3/7/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 3/7/2024 | Approved | ALEXANDER HANDY |
| FLOOD-Proofing Certificate | 3/7/2024 | Approved | ALEXANDER HANDY |
| Final | 3/7/2024 | Partial Approval | ALEXANDER HANDY |
| Green Building Final | 3/7/2024 | Approved | ALEXANDER HANDY |
| Green Building Rough | 3/7/2024 | Approved | ALEXANDER HANDY |
| HVAC-Final | 3/7/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 3/7/2024 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 3/7/2024 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 3/7/2024 | Approved | ALEXANDER HANDY |
| Final | 3/13/2024 | OK to Issue CofO | ALEXANDER HANDY |