9937-9939 N GERALD AVE 91343
Certificate Information: 9937-9939 N GERALD AVE 91343
- Application / Permit
- 23016-20000-22766
- Plan Check / Job No.
- B23VN09225
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan CONVERT (E) ATTACHED GARAGE TO ADU PER GCS 65852.2(e)(1)(A). WORK PER WFPP.
- Permit Issued
- Issued on 8/4/2023
- Issuing Office
- Current Status
- CofO Issued on 9/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2023 | ISIS ARGUETA |
| Corrections Issued | 7/19/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 8/2/2023 | ISIS ARGUETA |
| Plan Check Approved | 8/3/2023 | ISIS ARGUETA |
| Issued | 8/4/2023 | APPLICANT |
| CofO in Progress | 9/3/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
| CofO Issued | 9/9/2025 | RUBEN SALAS |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
Permit Application Clearance Information
| ZA Case | Cleared | 7/25/2023 | RUBEN VASQUEZ |
| ZA Case | Cleared | 7/25/2023 | RUBEN VASQUEZ |
| Address approval | Cleared | 7/26/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2023 | FERNANDO GIL |
| Grading Pre-Inspection | Cleared | 7/26/2023 | SERGIO VALENZUELA |
| Sewer availability | Cleared | 7/26/2023 | FERNANDO GIL |
Contact Information
| Contractor | Markarian Setrag; Lic. No.: 832632-B | , |
| Contractor | Pampa Investment Inc; Lic. No.: 832632-B | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/17/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 10/17/2023 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 10/17/2023 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/23/2023 | Corrections Issued | JAVIER RAMOS JR |
| Sewer | 10/23/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 12/4/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 12/4/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 12/4/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 12/29/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Rough | 12/29/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 12/29/2023 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 12/29/2023 | Corrections Issued | JAVIER RAMOS JR |
| Insulation | 1/24/2024 | No Access for Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/24/2024 | No Access for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 1/31/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 1/31/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 1/31/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 1/31/2024 | Approved | JAVIER RAMOS JR |
| Wood Frame | 2/13/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 2/28/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 7/3/2024 | SGSOV Not Ready | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/24/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 7/24/2024 | Approved | JAVIER RAMOS JR |
| Final | 7/24/2024 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 7/24/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 7/24/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 7/24/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 7/24/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 7/24/2024 | Approved | JAVIER RAMOS JR |
| Final | 9/30/2024 | Partial Inspection | JAVIER RAMOS JR |
| Green Building Final | 9/30/2024 | Approved | JAVIER RAMOS JR |
| Final | 9/3/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |